Decision Maker: Head of Housing Development
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
The appointment commenced on 24 July 2025 to
support the urgent re-procurement and delivery requirements of the
scheme. Owing to an administrative oversight, the required approval
for the waiver and direct award was not obtained prior to
commencement of services. This decision therefore regularises the
appointment and expenditure incurred to date and authorises the
continuation of services through the construction phase, practical
completion and defects liability period.
PPP has extensive knowledge of the project,
its development history, programme requirements, contractual
arrangements and funding obligations. This familiarity places PPP
in the strongest position to provide continuity of service and
support successful delivery through construction, practical
completion and expiry of the defect’s liability period.
The appointment ensures continuity of professional support at a
critical stage of project delivery and avoids the additional
mobilisation costs, duplication of effort and delays that would be
associated with appointing a replacement consultant. The Council
considers that retaining PPP represents the most efficient and
cost-effective option and will help mitigate risks to programme
delivery.
The Council considered undertaking a
competitive procurement exercise to appoint an alternative
consultant. However, due to the relatively low contract value, the
advanced stage of project delivery and PPP's existing knowledge of
the scheme, this option was rejected. Appointing a new consultant
would require a significant familiarisation period, create
additional mobilisation costs, reduce efficiency and increase the
risk of delays to project delivery. Accordingly, the direct award
to PPP is considered to provide the best overall value for money
and minimise delivery risk.
Publication date: 26/08/2026
Date of decision: 26/08/2025