Decision Maker: Delivery Director
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
It is recommended that the Delivery Director
approves to waiver 8.03 under CSO 10.01.1 b) and approve of the
waiver and award in accordance with CSO’s 10.01.1b, 9.07.1(c)
and 10.01.2 d) (ii) (iii), 18.01.01, 18.01.2(d) and
18.01.4(b).
Approves the implementation of Contract Standing Order 10.01.1 b)
and award a contract for HTVIA services for the Mallard Place
project to RIBA Stage 3 for a fee of £18,100 (excluding
VAT).
The direct award of Iceni will ensure a timely
delivery of design and development of Mallard Place to be able to
claim GLA SOS grant by March 2026. Iceni have an excellent
knowledge of the project and of Haringey and the GLA requirements,
having delivered Planning Consultancy services on the Mallard Place
project to date.
Iceni direct award and planned start in providing HTVIA services on
the project in May 2025, will be crucial in helping to achieve
Haringey’s commitment to build 3000 Council homes by 2031,
with current Stage 2 design indicating that 151 homes can be
delivered on the sites Block D and Mallard Place.
It is key to appoint Iceni on to the project asap so the assessment
services can be developed for the Local Authority and GLA
Planner’s, feeding into the Architect’s drawings as
well as the planning application and help us meet the March 2026
deadline for a SOS grant claim of up to £37,750,000.
The Council could decide not to procure these
services or direct award this contract to Iceni. This option is not
recommended as it would impact the delivery timescales of design, a
future planning submission and grant claim by March 2026. If the
March 2026 date is not achieved, this would ultimately impact the
Council’s Housing Delivery programme aspirations of providing
much-needed new Council homes, with potentially 151 homes not
delivered.
Publication date: 21/05/2025
Date of decision: 16/05/2025