Decision Maker: Assistant Director for Housing
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
It is recommended that the Interim Assistant
Director for Housing approves an award of contract to the value of
£66,400 to Altair for provision of the Programme Support
consultancy services for a period of 32 weeks.
There are long term plans for the growth of
the Programme team however, these long-term growth plans are being
dealt with as part of a wider re-structure of the Housing Delivery
Team which is ongoing. There is a need to provide the services now
as temporary basis until the restructure is completed to ensure
continuity of the service.
Without employing this interim resource, the Council will struggle
to resource and effectively run the programme function of the
Council House delivery team. By continuing this interim resource,
they will be able to ensure there is no gap in service or loss of
momentum to the programme.
An alternative option to appoint permanently
to the role cannot be considered as the Housing Delivery Team is
currently going through a re-structure. Therefore, any recruitment
is on hold until the re-structure plans have had full approval at
which point the Council will look to recruit to this role full
time.
Another option would be to appoint an alternative interim, however
an alternative interim would also need to undergo a lengthy
training process which there is not sufficient time or capacity to
undertake.
Publication date: 20/12/2024
Date of decision: 19/12/2024
Accompanying Documents: