Decision Maker: Assistant Director for Housing
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
It is recommended that the Assistant Director
of Housing approves a waiver by waiving off CSO 8.03 and an
approval of the waiver and award in accordance with CSO’s
10.01.1b, 9.07.1(c) and 10.01.2. d) (ii) (ii) to award a contract
Mechanical and Electrical (M&E) Engineering services for the
Mallard Place project to Max Fordham LLP to RIBA Stage 3
The direct award of Max Fordham LLP to RIBA
Stage 3 will ensure a timely delivery of design and development of
Mallard Place to be able to claim GLA SOS grant by March 2026. Max
Fordham have a detailed knowledge of the project and Haringey
requirements, having been the M&E consultant on Ashley Road
Depot, a recent similar-sized affordable housing project initiated
by the Housing Delivery Team.
Max Fordham LLP direct award and planned start in providing M&E
Engineering services on the project in December 2024, will be
crucial in helping to achieve Haringey’s commitment to build
3000 Council homes by 2031, with Levitt Bernstein’s initial
feasibility indicating that 168 homes can be delivered on the sites
Block D and Mallard Place.
It is key to appoint Max Fordham LLP on to the project asap as
there will be an urgent requirement for M&E designs and
clarifications/requirements which will feed into the
Architect’s drawings and help us meet the March 2026 deadline
for a SOS grant claim
The Council could decide not to procure these
services or direct award this contract to Max Fordham LLP. This
option is not recommended as it would impact the delivery
timescales of design, a future planning submission and award of
build contract by March 2026. If the March 2026 date is not
achieved, this would ultimately impact the Council’s Housing
Delivery programme aspirations of providing much-needed new Council
homes, with potentially 168 homes not delivered.
Publication date: 17/12/2024
Date of decision: 16/12/2024