Decision Maker: Head of Project Delivery
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
Approve a waiver of Contract Standing Order 8.03 (requirement to
obtain at least three competitive quotations) pursuant to Contract
Standing Order 10.01.2 (d) (iii).
To approve an award of contract to Raytel Ltd in the sum of
£11,885.22 and a contingency of £7,000.00 offering a
total award value up to £18,885.22 pursuant to Contract
Standing Order (CSO) 9.07.1 (c).
Reasons for the decision Condition works
initially planned to be completed during Summer 2024 have been
re-scheduled to 2025. This work includes replacement of Vulcanised
Indian Rubber (VIR) electrical cabling which runs from the
electrical intake room to the north and south switch-rooms. If this
fails between now and 2025 it’s intended to support the
schools power supply with a temporary generator and install
temporary electrical cabling to the impacted areas. This award
supports a call off arrangement with Raytel Ltd in the event a
generator is required for a hire period of 1 week which is intended
to facilitate the most essential remedial works sufficient to
reinstate any loss of power.
The reliability of providing such specialist equipment at short
notice is paramount to maintaining supply and minimising disruption
to the school. Raytel ltd who are an electrical contractor holding
a long-term working relationship with Haringey Council were asked
to provide a quotation for these works based on delivering a
suitably sized generator and undertaking temporary wiring within a
24-48-hour period limiting disruption to the school. Please note
the contingency allowance of £7,000 is based on a potential
requirement to retain the generator on site for a period of 5 weeks
as UKPN will be required to provide the final connection of the
temporary supply and it is recognised there is a risk of
delay.
In rescheduling condition works to 2025, a risk assessment was
completed which determined the most appropriate course of action
would be to make all prior arrangements to support implementation
of an action plan if required.
Do nothing – if the VIR cabling failed
before works commence in 2025 this approach would leave the school
partially without power and be detrimental to the quality of
teaching and learning.
Consideration was given to competitively tendering the work however
reliability of a known and well-established contractor was
paramount and based on this being of relatively low value for a
direct appointment is supported by the Head of Procurement,
pursuant to Contract Standing Order 10.01.1c.
The cost of these works has been reviewed by the Cost Consultant
appointed who have confirmed that this award represents value for
money.
Publication date: 26/11/2024
Date of decision: 24/10/2024
Accompanying Documents: