Decision Maker: Head of Programme Management
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
For the Head of Programme Management
Regeneration & Economic Development to approve a retrospective
contract and variation under CSO 10.02.1 (a) to enable PUP
architects to undertake design work for Eat Wood Green in its new
location at Wood Green Library.
The additional variation cost is £35,355 making the total
aggregated cost of the project £75,000.
The timeframe for the project remains the same with the completion
date for the design work being October 2024.
The reason for the decision is due to the
original contract (LBH006895) lapsing in October 2023, creating the
need for a new PO as the commercial agreement is still in
place.
In addition, challenges with the site including the need for large
scale repairs led the project to be moved from Bury Road to Wood
Green Library, have led to an increase in costs.
The original competitive tender process was completed in March 2022
and approved in April 2022 with the contract for design services
for the Eat Wood Green community growing project at Bury Road being
awarded to PUP Architects.
A design process was undertaken to RIBA Stage 3 and signed off for
the Bury Road site.
A do-nothing approach would have a detrimental
impact on the council’s capacity to deliver this project, as
the design team are central to delivery.
Launching a new tender process would hinder the council’s
ability to react quickly as a programme prioritisation.
Publication date: 04/11/2024
Date of decision: 04/11/2024