Bruce Grove Public Conveniences (BGPC) Refurbishment Works delivering a new Community Café Facility

Decision Maker: Assistant Director for Capital Projects and Property

Decision status: Recommendations Approved

Is Key decision?: No

Is subject to call in?: No

Decision:


For the Assistant Director of Capital Projects and Property to approve a variation of contract to DK-CM by £22,000.00 varying the approved contract sum from £248,327.75 to £270,327.75 as allowed under Haringey’s Contract Standing Orders 10.02.1a

Reasons for the decision:


DK-CM’s commission is based on agreed lump sum fees for RIBA stages 1-4, and a 12 month construction period for RIBA stage 5-6. Due to unforeseen delays the construction period has been extended and a fee adjustment for RIBA Stages 5-6 is required due to:

Alternative options considered:


As practical completion has been achieved and in RIBA stage 6 defects, changing consultancy resources at this late stage would be detrimental to the council in terms of time and cost. There are no available resources within the Council that have the capacity or expertise to deliver this cost consultancy resource in house.

Publication date: 28/08/2024

Date of decision: 20/08/2024