Decision Maker: Head of Programme Management
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
In accordance with CSO 10.0.02 (d) (ii) and
(iii), for the Head of Programme Management – Regeneration
and Economic Development, to approve a contract waiver for the
appointment of Civic Earth Ltd, for the provision of intrusive site
investigation services at Down Lane Park up to the value of
£11,900+ VAT.
A RIBA Stage 2 assessment of pre-existing
Geo-Environmental survey information was initially judged by the
design team engineers to provide sufficient information to affirm
the proposed Hub building foundation solution. As the Hub building
design has iterated through developed and detailed design, it has
become necessary to seek further, more detailed below ground
conditions information, so the proposed foundation solution can be
verified or modified accordingly.
Given the relatively late stage of the design process, this new
information is required urgently to avoid a negative impact on
design development, programme, and project costs. Civic Engineers
are part of the existing wider design sub-consultant team,
providing structural and engineering input, and there are time
efficiencies in engaging their sister company Civic Earth to
undertake the site investigations that are now required.
Civic Earth have provided a proposal and quoted fee for Stage 1
(window excavation) investigation and Stage 2 (cable percussion
borehole) investigation, allowing for the possibility that Stage 1
may prove inconclusive. The quoted fee for both stages is
£11,900.
It is noted that had the need for additional information been
identified earlier it would have been prudent to seek three
quotes.
Option 1 ‘Do Nothing’
This option was rejected. It would expose the council to undue
design, tender, construction, and financial risk to progress RIBA
Stage 4 (detailed designs) for without further, more detailed
information about the below ground conditions necessary to verify
or inform the modification of the proposed building foundation
solution.
Option 2 Seek three quotes.
This option was rejected. Given the relatively late stage of the
design process and the pressing need to obtain further, more
detailed information about the below ground conditions, it would
cause delays to design, programme, and likely start on site date,
to pause design to run a tender exercise.
Option 3 Approve contract waiver.
Civic Earth have provided a proposal and fee that is considered
sound and reasonable, and indicated an ability to mobilise quickly
and provide the information required within a timeframe that will
avoid any negative impacts on design development, programme and
start on site date. It is therefore recommended to appoint Civic
Earth Ltd to undertake intrusive site investigations. (Appendix
1).
Publication date: 03/06/2024
Date of decision: 05/03/2024