Decision details

Extension under Contract Standing Order 10.02 of a contract for Martin Arnold LTD, Construction Consultants to provide multidisciplinary services at Topham Square car park rear of 15-25 Risley Avenue N17 7HL

Decision Maker: Assistant Director for Housing

Decision status: Recommendations Approved

Is Key decision?: No

Is subject to call in?: No

Decision:

It is recommended that the Assistant Director of Housing approves the implementation of Contract Standing Order 10.02 to extend Martin Arnold LTD appointment by the value of £30,722.20 (inclusive of VAT).

Reasons for the decision:

The programme timetable for this scheme has extended by 8 months to 26 June 2024 compared to the milestones provided at tender stage.
Martin Arnold has procured and managed several sub-contractors (principally undertaken site surveys and necessary due diligence and forming part of the design and engineering team) during the design and planning stages the scale of this was not envisaged at tender stage.

Alternative options considered:

The Council could refuse the uplift in fee, this has been rejected because it is not reasonable to not consider appropriate requests for additional fees in line with the terms of the contract and would likely result in a legal challenge or a termination notice from the consultant. The value is reasonable for the extra services provided.
The other option considered was not to award this appointment at all. This would not support the delivery of the Council’s commitment to deliver four homes at Topham Square/Risley Avenue.

Publication date: 20/02/2024

Date of decision: 02/02/2024