Decision details

Approval to extend current Highways and Street Lighting Contracts and approval of the procurement strategy for a future combined Highways and Street Lighting Contract

Decision Maker: Cabinet

Decision status: Recommendations Approved

Is Key decision?: No

Is subject to call in?: No

Decision:

DECLARATIONS OF INTEREST MADE FOR THIS ITEM:

 

None

 

RESOLVED:

 

That Cabinet:

 

1.    Approved a variation to the existing Highways and Minor Improvement Works Term Contract, increasing its value from £98 million to £105 million for the remaining period of the contract to 30 June 2027, and approve a further variation beyond 30 June 2027 for a maximum period of 12 months to 30 June 2028, with an estimated additional value of £5 million, in accordance with CSO 2.01(d), which required Cabinet approval for any variation or extension with an aggregate value of £500,000 or more.

2.    Approved a variation to the existing Street Lighting Works Term Contract beyond 30 June 2027 for a maximum period of 12 months to 30 June 2028, with an estimated additional value of £2 million, in accordance with CSO 2.01(d), which required Cabinet approval for any variation or extension with an aggregate value of £500,000 or more.

3.    Approved the commencement of a procurement exercise in accordance with CSO 2.01(b), which required Cabinet approval before commencing a procurement exercise for proposed contracts valued at £500,000 or more.

 

Reasons for the Decision

 

As the highway authority, the Council had a statutory duty to maintain highway infrastructure in a safe condition for pedestrians, cyclists, and other road users. It was therefore necessary to maintain appropriate contractual arrangements to support delivery of the Council's highways and street lighting capital and revenue programmes, while also progressing longer-term procurement arrangements for future service delivery.

 

Alternative Options Considered

 

The option of taking no action was not considered viable, given the requirement to ensure the continued delivery of a substantial programme of highway, traffic management, and street lighting works over the coming years.

 

Procuring entirely new contractual arrangements to commence immediately following the expiry of the existing contracts on 30 June 2027 was considered but was not recommended in light of prevailing economic uncertainty and market conditions.

 

The option of bringing some or all of the works in-house had previously been the subject of a detailed review undertaken in 2023. The review concluded that the existing delivery model continued to offer the most effective and efficient means of delivering the required works and services, taking into account operational requirements, resource implications, and value for money considerations.

 

Publication date: 10/11/2026

Date of decision: 10/11/2026

Decided at meeting: 10/11/2026 - Cabinet