Decision Maker: Cabinet
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
DECLARATIONS OF INTEREST MADE FOR THIS ITEM:
None
RESOLVED:
That Cabinet, after considering the information within the exempt appendices:
Reasons for the decision
The recommendations
enabled the delivery of High Road West Phase 1A, which would
provide 61 affordable homes on Council-owned land. The development
would support the rehousing of more than half of the existing
residents of the Love Lane Estate into permanent homes in
accordance with the commitments set out in the Love Lane Landlord
Offer, which had previously been supported through a resident
ballot. As existing properties became vacant, subsequent phases of
the High Road West programme would be able to proceed.
Planning permission
for the wider High Road West scheme, including detailed consent for
Phase 1A, was granted in October 2021. A subsequent non-material
amendment was approved in July 2023. The site was therefore ready
to move into the construction phase, and the report represented the
final member-level approval required before
implementation.
Contractor A was
identified through a formal tender process. Approval of the
contract award and land appropriation enabled the Council to enter
into the construction contract and proceed with the development
works.
The Love Lane Estate
Management Plan was intended to ensure that the estate remained
safely and effectively managed prior to redevelopment. The plan
sought to support housing management, health and safety and
community safety responsibilities, while also improving the living
conditions of residents remaining on the estate during the
rehousing process.
The block at 2–32 Whitehall Street formed part of Phase 1B of the wider Development Agreement. As the earliest anticipated transfer of the site for redevelopment was not expected until 2028, the block remained vacant and was experiencing anti-social behaviour issues affecting the surrounding area. Demolition was proposed to address these issues and create the opportunity for interim uses of the site that could benefit the local community. Any temporary use would remain compatible with future redevelopment proposals.
Delegated authority
for future site security, decommissioning and demolition contracts
was intended to ensure that the Council could implement the Estate
Management Plan in a timely manner. The plan was designed to
address health and safety considerations, support the management of
vacant properties and maintain the effective operation of the
estate during phased redevelopment. It also sought to retain the
use of lower-rise blocks for housing where feasible during the
transition period.
Alternative options considered
Not proceeding with the housing development
The Council considered
not developing the site for housing. This option was not pursued
because it would not have supported the delivery of additional
affordable homes.
Not appropriating the land for housing purposes
The Council considered
not appropriating the land for housing purposes following
completion of the works. This option was not pursued because it
could have prevented the new homes from being occupied and
therefore hindered the delivery of the development.
Retaining Whitehall Lodge as temporary accommodation
The Council considered
retaining Whitehall Lodge for temporary accommodation use. This
option was not pursued because the site was required for Phase 1A.
It would also have left a partially demolished site that was
experiencing anti-social behaviour issues. In addition, the
building was not considered suitable for long-term temporary
accommodation use.
Not implementing the Love Lane Estate Management Plan
The Council considered
not implementing the Estate Management Plan and not delegating
authority to procure the associated contracts. This option was not
pursued because delays in securing the necessary services could
have reduced the Council’s ability to manage vacant
properties, address anti-social behaviour, maintain health and
safety standards and support phased rehousing
effectively.
Retaining 2–32 Whitehall Street until redevelopment
The Council considered
retaining 2–32 Whitehall Street and securing the building
until redevelopment commenced. This option was not pursued because
it would have continued to present risks associated with
anti-social behaviour and would not have allowed interim community
uses of the site to be explored.
The Council also
considered bringing the building back into residential use prior to
redevelopment. This option was not pursued because it would have
required substantial investment that was not considered
proportionate given the anticipated redevelopment timetable and the
fact that the block was already vacant.
Publication date: 14/07/2026
Date of decision: 14/07/2026
Decided at meeting: 14/07/2026 - Cabinet
Accompanying Documents: