Decision details

Report for approval of the contract for Phase 1(a) of the High Road West Scheme, demolition of 2-32 Whitehall Street, and the management plan for the Love Lane estate.

Decision Maker: Cabinet

Decision status: Recommendations Approved

Is Key decision?: No

Is subject to call in?: No

Decision:

DECLARATIONS OF INTEREST MADE FOR THIS ITEM:

 

None

 

RESOLVED:

 

That Cabinet, after considering the information within the exempt appendices:

 

  1. Approved the appointment of Contractor A, identified in the exempt section of the report, to undertake the demolition of Whitehall Lodge and 2–32 Whitehall Street and to deliver 61 new Council homes at High Road West Phase 1A, for the contract value and contingency amount set out in the exempt report.

  2. Approved the appropriation of Council-owned land within the Phase 1A site, comprising both General Fund and Housing Revenue Account land, for planning purposes under Section 122 of the Local Government Act 1972. The appropriation was to take place following demolition of the existing buildings on the site.

  3. Agreed that the appropriation for planning purposes was temporary and necessary to enable demolition, site preparation and construction works required for the development.

  4. Approved the use of the Council’s powers under Section 203 of the Housing and Planning Act 2016, following appropriation of the land, to override easements and other third-party rights or interests that could impede the development of the Phase 1A site.

  5. Approved the subsequent appropriation of the Phase 1A site for housing purposes under Section 19 of the Housing Act 1985 following practical completion of the new-build development.

  6. Delegated authority to the Director of Capital Projects and Property, in consultation with the Director of Finance and Resources, the Cabinet Member for Housing and the Monitoring Officer, to:
    • implement the appropriations referred to in the report and determine their timing;
    • take all necessary steps to enable reliance on Section 203 of the Housing and Planning Act 2016; and
    • agree the terms of, and authorise payment of, any compensation required as a result of exercising those powers.

  7. Delegated authority to the Cabinet Member for Housing to approve extensions to the construction and consultancy contracts up to the maximum value set out in the exempt section, subject to approval through the Housing Delivery contingency process.

  8. Approved the total scheme cost for Phase 1A as set out in the exempt report.

  9. Approved the issue of a letter of intent for up to 10% of the contract value specified in the exempt report.

  10. Approved implementation of the Love Lane Estate Management Plan and the associated budget set out in the exempt report. The plan included provision for future decommissioning and demolition, site security and investment in blocks scheduled for later phases of redevelopment.

  11. Approved the commencement of procurement exercises under Contract Standing Order 2.01(b) for site security, decommissioning and demolition works relating to the Ermine, Charles and Moselle blocks once residents had been rehoused and the blocks vacated.

  12. Delegated authority to the Cabinet Member for Housing, through a Cabinet Signing process, to approve the award of contracts for site security, decommissioning and demolition of the Ermine, Charles and Moselle blocks where contract values exceeded £500,000.

  13. Agreed a total budget of £1.1 million for delivery of the Love Lane Estate Management Plan.

  14. Delegated authority to the Director of Placemaking and Community Development to submit funding applications and receive and spend any funding secured in relation to temporary uses on the Love Lane Estate following demolition and before redevelopment, in accordance with Contract Standing Orders.

Reasons for the decision

The recommendations enabled the delivery of High Road West Phase 1A, which would provide 61 affordable homes on Council-owned land. The development would support the rehousing of more than half of the existing residents of the Love Lane Estate into permanent homes in accordance with the commitments set out in the Love Lane Landlord Offer, which had previously been supported through a resident ballot. As existing properties became vacant, subsequent phases of the High Road West programme would be able to proceed.

Planning permission for the wider High Road West scheme, including detailed consent for Phase 1A, was granted in October 2021. A subsequent non-material amendment was approved in July 2023. The site was therefore ready to move into the construction phase, and the report represented the final member-level approval required before implementation.

Contractor A was identified through a formal tender process. Approval of the contract award and land appropriation enabled the Council to enter into the construction contract and proceed with the development works.

The Love Lane Estate Management Plan was intended to ensure that the estate remained safely and effectively managed prior to redevelopment. The plan sought to support housing management, health and safety and community safety responsibilities, while also improving the living conditions of residents remaining on the estate during the rehousing process.

The block at 2–32 Whitehall Street formed part of Phase 1B of the wider Development Agreement. As the earliest anticipated transfer of the site for redevelopment was not expected until 2028, the block remained vacant and was experiencing anti-social behaviour issues affecting the surrounding area. Demolition was proposed to address these issues and create the opportunity for interim uses of the site that could benefit the local community. Any temporary use would remain compatible with future redevelopment proposals.

Delegated authority for future site security, decommissioning and demolition contracts was intended to ensure that the Council could implement the Estate Management Plan in a timely manner. The plan was designed to address health and safety considerations, support the management of vacant properties and maintain the effective operation of the estate during phased redevelopment. It also sought to retain the use of lower-rise blocks for housing where feasible during the transition period.

Alternative options considered

Not proceeding with the housing development

The Council considered not developing the site for housing. This option was not pursued because it would not have supported the delivery of additional affordable homes.

Not appropriating the land for housing purposes

The Council considered not appropriating the land for housing purposes following completion of the works. This option was not pursued because it could have prevented the new homes from being occupied and therefore hindered the delivery of the development.

Retaining Whitehall Lodge as temporary accommodation

The Council considered retaining Whitehall Lodge for temporary accommodation use. This option was not pursued because the site was required for Phase 1A. It would also have left a partially demolished site that was experiencing anti-social behaviour issues. In addition, the building was not considered suitable for long-term temporary accommodation use.

Not implementing the Love Lane Estate Management Plan

The Council considered not implementing the Estate Management Plan and not delegating authority to procure the associated contracts. This option was not pursued because delays in securing the necessary services could have reduced the Council’s ability to manage vacant properties, address anti-social behaviour, maintain health and safety standards and support phased rehousing effectively.

Retaining 2–32 Whitehall Street until redevelopment

The Council considered retaining 2–32 Whitehall Street and securing the building until redevelopment commenced. This option was not pursued because it would have continued to present risks associated with anti-social behaviour and would not have allowed interim community uses of the site to be explored.

The Council also considered bringing the building back into residential use prior to redevelopment. This option was not pursued because it would have required substantial investment that was not considered proportionate given the anticipated redevelopment timetable and the fact that the block was already vacant.

 

Publication date: 14/07/2026

Date of decision: 14/07/2026

Decided at meeting: 14/07/2026 - Cabinet

Accompanying Documents: