Decision Maker: Head of Housing Development
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
It is recommended that:
The Head of Housing Development approves awarding a contract to
Waterstone Design for Energy Consultant, MEP and Utilities surveys
and services in accordance with CSO 11.01 and 11.02 for the amount
of £23,550
+ VAT.
Additionally, approve an allowance for additional expenditure up to
a maximum of £7,500 to accommodate any necessary re-working
of SAP and overheating calculations as and of where they are
required.
The total aggregated value of this contract is £31,050 plus
VAT.
This contract pertains to an Energy Consultant, MEP and Utilities
surveys services for the delivery of affordable homes at the Kings
Road N17 Car Park development.
The Kings Road (N17) Car Park site has been
designated by Haringey Council for the direct delivery of new
Council homes. The project requires a multi-disciplinary
consultancy to manage the site from RIBA Stage 1 to 3.
The Council could opt not to appoint this
consultant; however, this decision would adversely affect and
hinder the delivery of new council homes. Conducting this survey is
a mandatory requirement