Decision Maker: Delivery Director
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
It is recommended that the Delivery Director
approves to waiver 8.03 under CSO 10.01.1 b) and approve of the
waiver and award in accordance with CSO’s 10.01.1b, 9.07.1(c)
and 10.01.2 d) (ii) (iii), 18.01.01, 18.01.2(d) and
18.01.4(b).
Approves the implementation of Contract Standing Order 10.01.1 b)
and award a contract for Wind and Microclimate modelling services
for the Mallard Place project for a fee of £10,500 (excluding
VAT).
The direct award of GIA will ensure a timely
delivery of design and development of Mallard Place to be able to
claim GLA SOS grant by March 2026. GIA have an excellent knowledge
of the project and of Haringey and the GLA requirements, having
delivered separate Daylight and Sunlight modelling services on the
Mallard Place project to date.
GIA direct award and planned start in providing Daylight and
Sunlight services on the project in May 2025, will be crucial in
helping to achieve Haringey’s commitment to build 3000
Council homes by 2031, with current Stage 2 design indicating that
151 homes can be delivered on the sites Block D and Mallard
Place.
It is key to appoint GIA on to the project asap so the modelling of
Wind and the Microclimate services can be developed for the Local
Authority and GLA Planner’s, feeding into the
Architect’s drawings as well as the planning application and
help us meet the March 2026 deadline for a SOS grant claim of up to
£37,750,000.
The Council could decide not to procure these
services or direct award this contract to GIA. This option is not
recommended as it would impact the delivery timescales of design, a
future planning submission and grant claim by March 2026. If the
March 2026 date is not achieved, this would ultimately impact the
Council’s Housing Delivery programme aspirations of providing
much-needed new Council homes, with potentially 151 homes not
delivered.
Publication date: 29/05/2025
Date of decision: 19/05/2025