Decision Maker: Assistant Director for Housing
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
It is recommended that the Assistant Director
of Housing approves to waiver 8.03 under CSO 10.01.1 b) and approve
of the waiver and award in accordance with CSO’s 10.01.1b,
9.07.1(c) and 10.01.2 d) (ii) (iii). Approves the implementation of
Contract Standing Order 10.01.1 b) and award a contract for
Landscape Architecture services for the Mallard Place project to
RIBA Stage 3 for a fee of £64,843 (excluding VAT).
The direct award of Levitt Bernstein to RIBA
Stage 3 will ensure a timely delivery of design and development of
Mallard Place to be able to claim GLA SOS grant by March 2026.
Levitt Bernstein’s landscape team have an excellent knowledge
of the project and of Haringey requirements, having delivered
similar services on the Ashley Road Depot and Cranwood House sites
for Haringey Council and being appointed as Architect on the
scheme.
Levitt Bernstein’s direct award and planned start in
providing Landscape Architecture services on the project in January
2025, will be crucial in helping to achieve Haringey’s
commitment to build 3000 Council homes by 2031, with Levitt
Bernstein’s initial feasibility indicating that c168 homes
can be delivered on the sites Block D and Mallard Place.
It is key to appoint Levitt Bernstein on to the project asap so
landscape drawings, parking etc can be developed which will feed
into the Architect’s drawings as well as the planning
application and help us meet the March 2026 deadline for a SOS
grant claim of up to £42,000,000.
The Council could decide not to procure these
services or direct award this contract to Levitt Bernstein. This
option is not recommended as it would impact the delivery
timescales of design, a future planning submission and award of
build contract by March 2026. If the March 2026 date is not
achieved, this would ultimately impact the Council’s Housing
Delivery programme aspirations of providing much-needed new Council
homes, with potentially 168 homes not delivered.
Publication date: 27/03/2025
Date of decision: 19/03/2025