Decision Maker: Head of Programme Management
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
For the Head of Programme Management –
Regeneration and Economic Development to approve the implementation
of Contract Standing Order 9.07.1c, the manner most expedient to
the efficient management of the service, and award a contract for
planning and heritage consultancy services to Planning Potential,
in the sum of £9,500.00, excluding VAT, from June 2024 to
December 2025
In October 2021, Planning Potential (PP) were
appointed to provide planning and heritage consultancy services for
a suite of projects under the High Streets Heritage Action Zone (HS
HAZ) programme. The original contract sum was £67,045.
Contract and PO extensions were subsequently approved, raising the
sum to £86,045 in August 2023. That contract ended in March
2024, in line with the anticipated closure of the programme, and
the PO has now been exhausted. The programme has, however, overrun,
due to a number of factors, including lack of resource in the Major
Projects team; the need to identify and secure additional sources
of funding to cover budget shortfalls; slow responses from and
inflexibility in negotiations with a third party; and lack of
resource in the Planning and Conservation teams. As a result,
additional planning and heritage consultancy services are required
to ensure all outstanding planning matters relating to the
incomplete projects are resolved.
This report is a request to approve the amount of £9,500 +
VAT for additional consultancy fees, thus extending the contract
value from £86,545 to £95,545.
This commission forms part of the wider Tottenham HS HAZ
regeneration scheme, which aims to make the high street in Bruce
Grove Town Centre a more attractive, engaging and vibrant place for
people to live, work and spend time and provide the catalyst for
change and additional investment from private owners. In this way,
it seeks to improve the long-term viability of the town centre to
serve its local residents and broaden its appeal to visitors.
This work would be wholly funded from match-funding, which is
contractually committed to the Tottenham High Streets Heritage
Action Zone.
The following alternative options were
considered:
‘Do Nothing’ - This option would be for the Council not
to create a new contract for planning and heritage consultancy.
This would limit the Council’s ability to follow through on a
number of live planning applications and submit further
applications needed as part of the construction phase of critical
elements of the HS HAZ programme.
New RfQ Process - The option of carrying out a new RfQ process to
appoint a planning and heritage consultant to deliver the remaining
services required was considered. This would significantly extend
an already much-delayed programme, whose funding is increasingly at
risk if projects cannot progress. Furthermore, as the existing
consultants, who have been working on the HAZ project since 2021,
PP are best placed to be able to deliver the necessary work in a
timely and cost-effective manner
Publication date: 04/09/2024
Date of decision: 29/07/2024
Accompanying Documents: