Decision Maker: Assistant Director for Capital Projects and Property
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
For the Assistant Director of Capital Projects and Property to
approve a variation of contract to Network Rail by £22,000
varying the contract sum from £69,679.60 to £91,679.60
as allowed under Haringey’s Contract Standing Orders
10.02.1a
The delivery of the project requires the Council to secure
technical approvals as part of the BAPA which is in place. Due to
project delays the fees agreed with Network Rail to review the
technical submission and monitor construction works on site have
reached their limit and further prolongation fees are due.
In addition to this as part of the refurbishment works technical
approvals are needed to ensure that designs and any works which are
to be completed on or near a Network Rail structure meet with their
performance and quality standards. Technical approvals to install a
fence on completion of the works on Network Rail land not included
in the original scope of work are required so safe access can be
provided to maintain and clean the building once it is operational.
Technical approvals for the fence are also needed as part of the
legal discussions to secure a lease/easement agreement for access
onto Network Rail land.
Not obtaining the required Network Rail technical approvals will
prevent the boundary fence being installed and access onto Network
Rail land to complete regular maintenance and cleaning of BGPC.
Completing maintenance from within the Councils land was also
considered. However, this was discounted as not all area of the
curtain walling and glazing can be safely reached.
Publication date: 28/08/2024
Date of decision: 21/08/2024