Decision Maker: Assistant Director for Housing
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
Approve a variation of the contract with
Levitt Bernstein Architects to increase the value by £56,448
to complete the quality monitor role for architecture and landscape
design work at the above site under Contract Standing Order
10.02.1(a). The revised overall cumulative value of the contract is
therefore, £390,653.
Planning condition 26 of the planning decision
notice dated 10 October 2022 states that Levitt Bernstein
Architects continues to be employed as project architect
Tendering out a new contract would not be in
keeping with the scheme’s conditional planning consent and
cost the Council additional money and time, so this option was
therefore rejected.
Publication date: 08/01/2024
Date of decision: 05/01/2024