Decision Maker: Assistant Director for Regeneration and Economic Development
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
This report seeks approval to award a 12-month
contract to Alban LLP for provision of Development Management
Consultancy services for the High Road West Regeneration Scheme,
for the sum of £107,250.00, in accordance with Contract
Standing Order 8.03.
The Council does not currently have the
inhouse resources to deliver the Development Management expertise
required to support the High Road West Regeneration Scheme.
Therefore, in accordance with CSO 8.03, a competitive procurement
was undertaken to obtain an experienced consultant to fulfil this
requirement. Alban LLP submitted the most economically advantageous
tender and therefore it is recommended that the contract be awarded
to them.
Not taking this action would represent a
substantial risk to the delivery of the scheme, including
financial, legal and programme risks
Publication date: 05/10/2022
Date of decision: 22/09/2022
Accompanying Documents: