Decision Maker: Director for Housing, Regeneration and Planning
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
It is recommended that the Director of
Housing,
Regeneration and Planning:-
• Pursuant to CSO 9.07.1(c) approves the award of a contract
to Hughes & Salvidge Limited for demolition services (as
described in the report) for the sum of £119,500.00
• Approves the associated consultancy fees of up to
£38,022.50, payable to Ridge and Partners LLP.
The Moselle School site is a key
‘opportunity site’ in
the wider Broadwater Farm regeneration scheme. The demolition is
being proposed now so most of the works can take place during the
summer holidays during which time fewer children will be attending
the school which is adjacent to the site. This has been
specifically requested by the school as we work with them to bring
forward a development that benefits both the estate and school. The
contract needs to be awarded the week commencing 19 July 2021 in
order to achieve a start on site in early August 2021.
The site also presents an opportunity to bring forward delivery of
much needed new council homes. The former school is empty, and
demolition is required to enable the timely construction of new
homes.
A compliant tender process has been undertaken via the DPS portal.
Four compliant bids have been received and quantitative and
qualitative analysis has been undertaken by Officers and supported
by Ridge & Partners LLP acting as Project Managers.
The winning bid was fully compliant with requirements, scored the
highest on the qualitative submission and the price is 60% lower
than the
initial cost estimate.
Officers could not ‘do nothing’,
the demolition of the
former school is required to enable the construction of the new
council homes.
The option of undertaking the demolition as part of the main new
build works was considered. This was rejected as it would add
additional time and risk to the main programme. The new homes
programme will not start until late 2022, so there is a good
opportunity to bring forward the demolition of the school, and
undertake any other enabling works, to accelerate the delivery of
new homes and de-risk the main programme. This will help ensure
that the council secures the maximum amount of grant available to
fund replacement homes on the site.
This would also allow the school to be demolished over the summer
holidays, thereby reducing disruption to the adjacent schools (The
Willow and The Brook).
Publication date: 20/08/2021
Date of decision: 02/08/2021