That the Assistant Director for Housing: -
1) Approves the award of contract to UK Gunite Limited for the quoted sum of £151,881 with a contract period of 20 weeks.
2) Approves the total project fees of £19,737 and notes the cumulative project cost of £171,618.48.
3) Approves the recommendations in the exempt part of this report.

Reasons for the decision:

Approval of the scheme quotation is required to allow essential urgent main flat roof renewal works to start on site. UK Gunite Limited have submitted the most economically advantageous tender.

Alternative options considered:

Haringey Council has responsibility for
maintaining the structural integrity of its housing
stock under the Housing Acts. The option of not
undertaking these repairs would leave the
Council open to legal challenge and future
disrepair claims.

Publication date: 04/05/2021

Date of decision: 26/05/2021