Additional costs to the major void works at 178 Mosellle Avenue, Noel Park, N22 6EX.
Decision Maker: Interim Assistant Director for Housing
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
Decision:
That the Assistant Director for Housing,
authorises the additional contract costs of £19,144.00.
Reasons for the decision:
The additional works were uncovered
following
a site inspection by Building Control and considered necessary to
be carried out at the construction phase of the project.
This is to
ensure that the property meets the Decent Homes and current Health
and Safety standards
Alternative options considered:
The option of doing nothing was not
considered.
This is because, as the landlord, Haringey Council must comply with
current
Health and Safety standards and ensure the property is deemed fit
to occupy.
Publication date: 01/07/2020
Date of decision: 24/06/2020