Decision Maker: Assistant Director for Regeneration and Economic Development
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
For the Assistant Director for Regeneration
to:
(i) approve the sum up to £49,999 for services to support
delivery of the Reopening High Streets fund project.
(ii) award We Made That consultancy services in accordance with
paragraph 6.22, to carry out the design of temporary street and
public realm interventions in town centres to promote safe access
and to support the financial health and viability of businesses
during the Covid-19 crisis.
(iii) approve the waiver of the usual requirement for tendering
under Contract Standing Order (CSO) 8.03 as allowed under CSO
10.01)b) in order to enable the decisions in (i) and (ii)
above
We Made That are considered to be the only
practice already under contract with Haringey Council, who could
deliver the project on time in accordance with the critical urgency
of ensuing safe access to town centres within the timescales of the
‘lockdown’ easing programme. Designers also have the
experience and knowledge to deliver the work to a high
standard.
As such, a waiver of tendering is being sought on the basis that
the circumstances are considered to be genuinely exceptional under
CSO 10.01.2(d)(iii).
If a standard procurement route were applied with a tender process,
it would be several weeks before design could start to be developed
which would significantly delay the programme and could potentially
increase the risk for visitors to town centres and businesses in
relation to health and safety requirements related to CV19.