Decision Maker: Assistant Director for Regeneration and Economic Development
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
That the Assistant Director for Regeneration
and Economic Development approves the award and waiver, in
accordance with CSO 9.07.1(c) and CSO 10.01, to Emma Smith for the
completion of the artistic interventions for Penstock Tunnel for
the fixed maximum value of £25,000.00
The preferred approach for commissioning the completion of the
designs for Penstock Tunnel is to directly contract with Emma
Smith. This would both ensure design consistency within the project
and allow the project to be delivered within the programme
constraints.
Emma Smith has in-depth knowledge of the project, having previously
developed the designs for Penstock Tunnel to RIBA stage 3, in
partnership with appointed principal designers We Made That LLP.
Hence the services sought are a natural extension. Emma will
continue her role as part of the delivery team and delivery of the
artworks will be via Haringey Council’s highways
contract.
A waiver of tendering is being sought on the basis that it is
considered to be within the Council’s overall interest under
CSO 10.01.
The alternative approach would be to procure
an artist through a three-quote tender process, this would add up
to 8-10 weeks to the programme and would affect the completion of
the project and the time dependant constraints. Furthermore, Emma
Smith was selected as the successful artist via a procurement
process that involved, local stakeholders, Councillors, Heartlands
School, principal designers We Made That and Haringey
officers.
Given RIBA Stage 0-3 have already been started by Emma Smith, it is
unlikely that a new team would be able to deliver the work without
incurring additional and unnecessary fees. The new team would need
to familiarise themselves with the work which has already been
carried out. Potential fundamental changes to designs and delays
will impact upon the necessary preliminary works and current scheme
timeframes.
Publication date: 25/06/2020
Date of decision: 25/06/2020