Decision details

Mound Removal Works/Ferry Lane

Decision Maker: Head of Project Delivery

Decision status: Recommendations Approved

Is Key decision?: No

Is subject to call in?: No

Decision:


To request approval to vary a contract with Fulkers Consultancy Ltd by £9,163.00 increasing their existing contract from £16,882.00 to £26,045.00 as allowed under Haringey’s Contract Standing Orders (CSO) 10.01.2 (a).

Reasons for the decision:


Fulkers Consultancy Ltd were awarded a contract in January 2019 for multi-disciplinary design service to remove a mound consisting of builder’s rubble and contaminated soil. The value of the award was £16,882.50 based on an initial projected construction cost of £100,000.00. Initial investigations, intrusive surveys, design development and projected final account offer a revised construction contract value of £256,100.00, therefore based on a pre agreed fee rate of 10.17% the total amount payable for the works carried out by Fulkers Consultancy Ltd will be £26,045.00.

Alternative options considered:


There are no resources within the council that have the capacity along with the necessary experience, qualifications and expertise to deliver this service in house.

A re-procurement exercise would not have facilitated removal and reinstatement works during the summer school holiday.

Publication date: 14/01/2020

Date of decision: 11/11/2019