Decision Maker: Director of Housing, Regeneration and Planning
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
It is recommended that the Director of
Housing, Regeneration & Planning approve the waiver of Contract
Standing Order 08.03 and approve the implementation of Contract
Standing Order 10.01.2.d to directly appoint KCA for the value of
£153,177 to complete design work up to planning submission
(RIBA Stage 3).
KCA have already started work on 10 sites, all
of which have progressed to a pre-app stage. KCA have pre-existing
knowledge of the sites and would be ready to start immediately.
They will also be able to save the Council time by using their
historic knowledge of the schemes to effectively and efficiently
complete the design work to planning. In addition, appointing KCA
will help save the Council money as they have only quoted to
complete the remaining design work whereas other architects are
more likely to charge large sums for transitional works.
A mini competition could take place, but this
would be very time consuming from a procurement and project kick
off perspective as most schemes would need to be reassessed and
progressed from the beginning. Tendering out a new contract would
cost the Council additional money and time; this option was
therefore rejected.
Publication date: 30/07/2019
Date of decision: 11/07/2019