Decision Maker: Assistant Director for Area Regeneration
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
For the Assistant Director for Regeneration to
approve a waiver of the requirement under CSO 8.03 to undertake the
request for 3 quotes procedure in order to make the contract award
to Jan Kattein Architects, for design services from RIBA Stage 2-7
and contract administration to a maximum value of £20,000. In
addition to approve the issue of a letter of intent, in accordance
with CSO 9.07.3, to Jan Kattein Architects in the amount of
£2,360. For the order of works to undertake designs to RIBA
Stage 2 (£1960) and QS report for Stage 2
(£400).
The preferred approach for commissioning the
design and contract administration is to directly contract with Jan
Kattein Architects. This would both ensure design consistency
within the project and allow the project to be delivered within the
programme constraints.
Jan Kattein has in-depth knowledge of the project, having
previously conducted designs to RIBA Stage 1 and the services
sought are a natural extension to the previous services provided to
the Café leaseholder, to the extent it would provide better
value than engaging an alternate provider whereby transitional
costs need to be considered.
A waiver of tendering is being sought on the basis that it is
considered to be within the Council’s overall interest under
CSO 10.01.
A letter of intent is needed to ensure that Jan Kattein can
commence further design works as soon as possible to meet project
deadlines and progress to RIBA Stage 2 and QS Stage 2 report.
Consideration was given to subjecting the
requirement for the advisory services to competition in line with
the Council’s policy of obtaining competitive quotations for
contracts of this value. The conclusion reached is this approach
would incur unnecessary delays and costs to the Council, as Jan
Kattein Architects have previous knowledge of the project and have
completed initial studies and surveys for RIBA Stages 0-1.
Appointment of another service would add significant delays and
have a negative impact on the Council’s reputation in
promoting a local business and could incur further budgetary
costs.
Publication date: 07/06/2019
Date of decision: 06/06/2019