Decision Maker: Overview and Scrutiny Committee
Decision status: For Determination
Is Key decision?: No
Is subject to call in?: No
OVERVIEW OF THE TECH REFRESH PROJECT – a presentation by the Executive Member for Organisational Development and Performance (Agenda Item 3) and EXECUTIVE MEMBER QUESTIONS (Agenda Item 4)
As it had not been possible to provide written answers ahead of the meeting these were laid round. The Chair adjourned the meeting for 15 minutes to give Committee members the opportunity to read them.
The Executive Member for Organisational Development and Performance made a short presentation on the history of the Tech Refresh Project. Lessons were learned from this project and recommendations made by the District Auditor were being implemented.
The Committee considered the Exec Member responses to written questions (attached). In response to Members supplementary questions, the Committee was informed, amongst other things, that :
The original Tech Refresh budget was £9m. Current expenditure to date was £19.6m.
The main reasons for the overspend were investigated by the District Auditor and the conclusions are set out in their report of January 06.
The E-Government Advisory Board and the Customer Services Working Group had been amalgamated.
Gartner carried out the original study into proposed IT enhancements in 2002. Deloitte drew up the architecture and specification and Northgate carried out the implementation work.
The preparatory cost of the project was £150k, this was separate to the budget.
The Section 151 Officer (the Director of Finance) had satisfied himself that there was not a conflict of interest in using Deloitte’s on this project.
All aspects of the DA report were accepted and were being implemented.
It was confirmed that most of the officers who worked on the project were still employed.
Consultants were not able to commit or authorise payments on the project, on behalf of the Council.
The project was delayed in part due to procurement problems and because the hardware was robust but the software integration and networking raised problems.
The overspend became apparent in May 2003, but the need for major additional expenditure was identified in 2005.
Serious consideration was given to abandoning the project but due to the risk to Council systems and the loss of potential benefit, it was decided to make additional resources available.
The Executive Member of ODPM was briefed on the Tech Refresh project when he took up his portfolio.
A Value for Money review will be commissioned in June 2006, once the poject had been completed.
Scrutiny Committee Members were disappointed that the written answers were not circulated in advance of the meeting and at the level of response. During the course of questioning, further information was requested, including:
· A more detailed breakdown on project dates and member attendance at project meetings from December 2003.
· A copy of the original detailed budget for the project and detail on how additional was allocated and when.
· The identification of all contractors involved on the project and their role, in addition to Gartner, Deloitte and Northgate.
· Copy of the original report by Gartner, who proposed IT enhancements.
· Copy of the former Chief Executive and Director of Finance’s written response to the overspend together with any documents thereon supplied to Executive Members
· A copy of the Terms of Reference of the further investigation, commissioned by the Leader
· That the written answers be expanded by the inclusion of the relevant sections of the DA Report and that they be re-circulated.
RESOLVED:
1. The time being 10.30pm, the Committee resolved that the meeting be adjourned until 2pm on 9 March 2006 and that necessary arrangements be made by the Head of Democratic Services.
2. The information requested, including the revised Questions and Answers, be circulated prior to the meeting.
At the reconeved meeting on 9 March 2006, at 2pm, the following Members of the Committee were present:
MEMBERS: Councillors *Bull (Chair) *Harris (Vice-Chair), *Bevan, *J Brown, *Davies, *Dawson, and *Winskill.
Co-optees: Mr. B. Aulsberry and Mrs. I Shukla (REJCC non-voting Representatives) *Mrs. C Bhangwandeen plus 2 Vacancies (parent governors), L. Haward and 1 vacancy (Church Representatives).
* Members Present
SC152 COMMUNICATIONS AND APOLOGIES FOR ABSENCE
Apologies for absence were received from Mr. B. Aulsberry and Mrs. I Shukla.
SC153 OVERVIEW OF THE TECH REFRESH PROJECT (RECONVENED ITEM) – a presentation by the Executive Member for Organisational Development and Performance (Agenda Item 3) and EXECUTIVE MEMBER QUESTIONS (Agenda Item 4)
The Executive Member for Organisational Development and Performance (OD&P), Councillor Sulaiman, was thanked for providing answers given to him by the Committee (these can be found at Appendix A to these minutes - below). He then gave answers to supplementary questions put to him by Councillor Winskill as follows:
Q To supplement the written answer to his question 1, Cllr Winskill asked when the project scale was increased from 2500 assets to 4700?
A Justin Holliday (JH) replied that he was not sure where the 2500 figure originated from. The reason for the increase in assets was because throughout the life of the Tech Refresh project, the number of users had increased.
Q How much consultation went on in relation to the whole Tech Refresh project?
A JH replied that it there was relatively little consultation undertaken because there was no integrated framework to do so the pre-Tech Refresh period.
Q In respect of page 28 of the Gartner Report (May 2003), how much work was done to overcome the pitfalls of delays in the network, which made performance appear to be slow? What was done to solve these problems?
A Councillor Takki Sulaiman (TS) replied that the understanding was that access speed was not bad and that it was subject to regular inspections. There is a quality of management as opposed to programme choice.
JH stated that they needed to ensure there are thich clients to ensure consistency in speed. There was network speed information available and he was satisfied that everything was done to overcome problems.
Q To supplement the written answer to his question 3, with reference the summary financial position (as at May 2005) for the Tech Refresh project, how is “delivery” (costed at £7.2m) defined?
A JH replied that remedial action had contributed to extra spending on the delivery of the project.
Q To supplement the written answer to his question 4, when did the project leader leave the Council?
A JH did not re-call the exact date, but indicated that it was before the election of the current Executive Member for OD&P. Deloitte took over prior to bringing the project back to an in-house project management set-up. There was a full handover at this time.
Q To supplement the written answer to his question 8, how far did the previous Executive Member for OD&P get involved in the Tech Refresh project?
A TS replied that there was clear guidance on where the Executive Member and lead officers took part in the project. He stated that some meetings took place in private and were not minuted and that this was appropriate.
The Chair of the O&S Committee asked when the spending levels for the project became a policy issue and the Executive Member get involved – and if he was given proper advice? TS replied that the expenditure was reported through normal Council procedures. TS admitted that the reporting to Members was not as strong as it should have been highlighting the need to strengthen project management mechanisms by reporting directly to (Executive) Members. TS talked about a new regime to report any expenditure above £25k that had recently been introduced, but that this was not the case at the time of the early stages of the project.
Councillor J Brown asked if there was an advisory committee/steering group in place and why was the e-Government Advisory Committee (eGAC)not involved in the Tech Refresh? TS replied that this committee was disbanded in July 2005 in order to bring together the e-Government and Customer Services themes. The eGAC was concerned with government target setting. The Customer Service Working Group subsumed all of the work of the the eGAC and reports to the Executive in an advisory capacity. It receives a full progress report on Tech Refresh. TS indicated that in February 2006, a new group was commissioned to address all issues relating to the progress of the project.
Councillor Winskill suggested that there was no evidence that the previous Executive Member for OD&P took an active role in the progress of the project. JH replied that there was no need to disclose information from private meetings. Numerous meetings took place between officers and Executive Member on a day-to-day basis and these were not minuted.
The Committee felt that it was not necessary to invite anyone other than the current Executive member and lead officers to address the Committee’s concerns.
Q To supplement the written answer to his question 12, the Committee was asked to consider requesting the Executive for Finance to provide an audit trail on expenditure relating to change requests during the project.
A JH replied that the project did not exceed agreed budgets at point it was at. There were no audit trails available.
Q To supplement the written answer to his question 17, there was a request to clarify the answer with an update to change management.
A JH provided clarity.
Q To supplement the written answer to his question 20, can the District Auditor answer the question of why overspend was not picked up during its investigations? Also, Councillor Bevan asked if the District Auditor had requested an audit, and how many times the Audit Committee met, and what was its role in the project?
A JH replied that there was a rolling programme of work for the Internal Audit, and that liaison at Member level with the District Auditor took place in July 2005.
Q To supplement the written answer to his question 23, why were there no staff disciplinaries or blame?
A TS replied that this was always an issue when things go wrong. District Auditors were brought in to fin out who made/where decisions were made. There was not one member of staff to blame because there was too wide a failing/systemic problems. JH added that it would be the Head of Paid Service who would decide on disciplinary procedures. JH also added that the findings of the District Auditor’s report highlighted the issues relating to blame (Audit Commission Performance Summary Report January 2006 para.34).
The Committee was advised by the Legal Services Representative, that if it wished to discuss the conduct of specific individuals in relation to the project, then it should consider passing a motion to hold that art of the meeting in private under the exemption clause. The Committee declined to take this route of action.
TS added that the responsibility and accountability for the success and failings of the project rested with the Executive, and confirmed that it was essentially the Executive’s failings that prevented adequate project management systems in place.
The Committee thanked Councillor Winskill for his questions and the Chair invited questions from other Members of the Committee.
Q Councillors Harris and Bull (Chair) stated that they were keen to see that in future, in order to avoid systemic failings, there are robust systems in place. Members need to be assured that there is a formal body which will provide an update on the Tech Refresh project and stem the overspend.
A TS replied that Members were not kept informed adequately, but that a new system to remedy this was now in place since it had been ratified by the Executive on 21 February 2006. This system will ensure that problems are not repeated, because there are safe-guards above spending levels of £25k. All of the Council’s existing and future projects are/will be subject to these new mechanisms.
Q To supplement the written answer to his questions 24 and 28, why did it take three months to request an investigation by the Audit Commission?
A JH replied that the decision was made at the end of June 2005 and formally approved in July after all options were considered.
There was a point of order requested by Councillor Dawson in relation to requests for information obtainable under the Freedom of Information Act. The Committee was advised by the Legal Services Representative that applications for Freedom of Information requests were dealt with by respective departments and that certain information was restricted under Section 36 of the Act.
Q Councillor Davies asked if the Head of Paid was intervening to curb the overspend in the period between realising the overspend, and inviting the Audit Commission to investigate?
A TS replied that there had been numerous discussions with the Chief Executive, senior officers and Members at all stages of the project.
Q To supplement the written answer to his question 33, can clarity be given on how many reports were produced relating to the project overspend.
A JH clarified that there was the District Auditor’s Report, a Value for Money Report, and that a post-Review would be necessary from the Executive Member assessing whether the project had delivered value.
Q Councillor Davies asked who would be conducting a Member/Officer interface review.
A TS replied that this would be undertaken by external consultants led by the Head of Paid Service.
The Committee thanked Councillor Winskill for his questions and the Chair invited supplementary questions from other Members of the Committee.
Q To supplement the written answer to her question 43, Councillor J Brown asked if the Executive Member was satisfied that this sort of systemic failures could not happen again.
A TS replied that there was now a much more robust system in place that would mean that a repeat of past failings was much less likely than in previous times.
RESOLVED:
The Committee noted that:
Part 1
1.1 IT is an ancillary service that relates to the operational performance of each Council business unit.
1.2 The Tech Refresh project was budgeted to cost the Council £9million but has cost the Council £19.6million.
1.3 The Audit Commission has investigated the Tech Refresh Project and published a report, dated January 2006, which the Overview & Scrutiny Committee welcomed.
The Overview & Scrutiny Committee concluded that the Tech Refresh overspend raised these questions, that have been fully answered by Audit Commission report, January 2006, and the Executive Member for Organisational Development & Performance:
Part 2
2.1 The IT provision throughout the Council.
2.2 The objective of the Tech Refresh Project.
2.3 The Tech Refresh Project implementation process.
2.4 The level of the overspend.
2.5 The items and services upon which the Tech Refresh budget and overspend were spent.
2.6 The responsibility and control for authorising budgets and the overspend.
2.7 The level of reporting to and control over the project implementation and budget authorisation carried out by the Executive Members for Finance and Organisational Development & Performance.
2.8 Future processes for validating project budgets.
2.9 Future processes for project assurance in terms of the continuing business case, technical standards and quality and whether the users specifications are met.
2.10 Future processes for budget authorisation and monitoring by the Executive Member for Finance.
2.11 The appropriate level of delegation to officers and the mechanisms for reporting to Executive Members and Councillors.
The Overview & Scrutiny Committee further concluded that the progression of the Tech Refresh project raised these questions, which have not yet been fully answered. Executive Members should report back to Overview & Scrutiny Committee on these issues:
Part 3
3.1 Future processes for ensuring that officers report to Executive Members on projects, the project control by Executive Members and the project review by Executive Members.
3.2 What is being done to implement of the recommendations in the Audit Commission report.
3.3 A report back on the outcome of any future follow-up meeting between the Council and the Audit Commission.
3.4 The final operational impact of the Tech Refresh project once it is complete. This should cover an assessment of the value for money of the Tech Refresh project.
INFORMATIVE
In reaching the above decisions, Councillors Davies and Winskill were noted as voting against 2.6 and 2.7 because they felt that these recommendations should have come under Part 3 of the decision.
APPENDIX A
Special Overview And Scrutiny Committee
Thursday 9th March 2006
Overview of the Tech Refresh Project
Questions to Cllr Sulaiman
Introductory comment
Members of the Committee have now received a presentation about the project and at the first part of the meeting last week, an initial opportunity to review the answers to the questions put to me. The matters set out in the questions have been the subject of a thorough external review, commissioned by the Council, conducted by the District Auditor. The District Auditor’s report was received by the Executive in open meeting on 18 January 2006 and the action plan in response to this reviewed was considered and agreed at the Executive on 21 February 2006.
Given this and in order to assist the deliberations of the Committee, the answers set out in this document cross reference to the District Auditor’s review and the other documents in the public domain. Given the additional time afforded by the Committee’s decision to reconvene, I have attempted to provide a more comprehensive set of answers in one place. However, this was a big and complex project and there are points where a cross reference to another document is necessary.
The background documents to which I have cross referred are:
Questions are shown in italic with the answers in standard font. The extracts from other reports are shown on boxes. I have attached at Appendix 1 to the answers the Action Points from the first part of the meeting to either answer them or cross refer to how they have been addressed in the main report.
Questions from Cllr Winskill
Project commissioning and budget process
1. Why was the project commissioned? What were the overall objectives of the project and what did it hope to deliver?
This is set out in the report to the Executive on 10 June 2003 and in the presentation to this Committee last week.
Original Objectives
• Replace a time expired infrastructure, upgrading to new technology for
– Network
– End User equipment
– Servers
– Operating system and Applications including email
– Physical Locations
• Establish a physical and technical environment which is less likely to fail and provides effective business continuity in the event of a disaster
• Promote a more flexible infrastructure which allows staff to work in any Council building, allows ‘hot desking’ and reduces the cost of office moves
• Reduce the on-going cost of managing the infrastructure with key elements, such as desktops, having extra lives
• A modern infrastructure which enables joint working with our partners, compliance with national standards, enables mobile working and supports e-government.
Additional objectives
• Increased security to reduce risk from active and emerging threats
• Improved network connections to over 100 smaller sites
• Increase and systematise the data storage available due to the increase in electronic data stored by the Council resulting from successful implementations of E-Government initiatives
• Absorbed the 25% increase in established usage from 3,800 to over 4,700 assets
• Delivered project development in parallel with deployment and build of new infrastructure due to urgent business need. These included:
• Siebel 7.7 upgrade
• Manhattan implementation
• Modern.Gov
• SAP Supplier Relationship Management which included 1-1 support during the training phase.
• Web casting
Project scale
• over 4,700 assets
• over 300 applications
• 45 terabytes of data storage
• 74 sites on WAN or LAN and 140 on broadband
• two data centres with over 300 servers
• all in the context of:
– nearly 2000 business as usual change requests over the deployment period
– extensive office move programme
2. How was the project budget developed?
This formed part of the District Auditor’s review and the conclusions are set out in paragraphs 21 – 23 of his report:
|
Para 21 |
The original project for the budget was reported to the Council’s Executive in June 2003, with capital costs of £5.3 million and ‘upfront project costs’ of £3.7 million, funded from a mixture of capital and revenue sources. |
|
Para 22 |
There is no evidence that the Project Initiation Document (PID), on which the budget was based, was prepared with appropriate input from Corporate Finance. In addition, reliance appears to have been placed on the review carried out by external consultants, referred to above, as an independent validation of the original budget. However, there is no documentary evidence that the review commented on the robustness of the Council’s costing of the project, nor indeed had such assurance been commissioned in the terms of reference for the review. |
|
Para 23 |
It would appear, therefore, that the initial budget for the project was not subject to adequate challenge. The finance comments in the June 2003 report to the Executive did not provide a view as to whether the costings were soundly based, but noted that savings of £1 million per annum had been assumed in financial plans. |
The criticisms set out above have been addressed in the Executive’s action plan of 21 February, in response to recommendations 1 and 2 (which introduce tighter controls over budget setting) and recommendation 7 (which sets out the approach to external challenge and validation of project proposals.
3. Please submit to this Committee the original budget and the current revised one with a commentary indicating where the changes are and the financial value of those changes.
The amendments to the project budget were reported to the Executive on 14 June 2005. This formed part of the District Auditor’s review and the conclusions are set out in paragraphs 24 – 27 of his report:
|
Para 24 |
Once under way, the project suffered from major cost overruns. As reported in the Executive Member Briefing of 10 May 2005 by the ACE, by August 2004 the overall project budget had increased from £9 million to £12.7 million, and the overall estimate stood at £24.6 million by April 2005. The external partners absorbed some £5.5 million, resulting in a revised estimate of £19.1 million, still more than twice the original budget. |
|
Para 25 |
According to the ACE briefing, the increased expenditure primarily occurred in the ‘people costs’ of the project, specifically: · the decision to engage external consultants as providers of change management resource given the inability of Council officers to provide the inputs assumed in the PID; · additional complexities identified during detailed planning, leading to further expenditure on design; and · original and material poor scoping of the work. |
|
Para 26 |
Our audit has identified additional people costs incurred through change management and change requests as the two areas resulting in significant additional costs to the project. It is clear that the original budget was based on incorrect assumptions as to the cost of the change management requirement, and the overall complexity of the scheme. |
|
Para 27 |
In November 2005, the Council identified further potential slippage and subsequently additional costs on the tech refresh project. There remain concerns, therefore, that the current budget may not yet be sufficiently robust. |
The criticisms set out above have been addressed in the Executive’s action plan of 21 February, in response to recommendations 3 and 4 (which cover change control procedures) and recommendation 10 (which covers reporting to project boards.
The full budget trail is set out below.
|
Summary financial position (as at May 2005)
Notes Explanation of variances 1 The cost overrun in this area is a function of three factors: extension of time, the provision of programme management between August 2004 and April 2005 and additional complexities (in terms of number of sites and volume of applications) revealed during the detailed planning. 2 Change was originally intended to be a Council function. The cost over run is because this had to be performed by Deloittes. 3 The cost overrun in this area is a function of three factors: original and material misscoping of the work by Northgate, additional complexities (in terms of the number of sites and volume of applications) revealed during the detailed planning and the expert resource we have had to bring in to deliver on the designs. 4 The cost overrun in this are is primarily due to additional hardware requirements, a function of the number of applications to be run in the citrix environment. 5 The report to the Executive on 14 June 2005 set out proposals on how this shortfall would be funded for agreement.
Notes on remedial action The remedial action has reduced the anticipated total cost by £5.5million. Additional costs of £4.1 million to the Council direct offset by, in the case of: 5 Deloittes revenue forgone of £1.5 million and write offs of ££0.3 million. 6 Northgate revenue forgone of £5.5 million and write offs of £2.3 million. |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
|
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
It is also worth noting that the revised budget was reported to Council, as part of a written answer, on 18 July 2005, which is attached.
4. In view of the IT industry’s notorious reputation for overspend, what precautions were taken to minimise any overspend on this project?
This formed part of the District Auditor’s review and the conclusions are set out in paragraphs 37 - 48 of his report:
|
Para 37 |
Responsibility for controlling the project budget rested with the ACE, the Head of ICT and the Project Leader. The Project Leader, who has left the Council, had day-to-day control of budgets. From the documents available to us, it is unclear how budgetary control was exercised. |
|
Para 38 |
Until recently, the Highlight Reports adopted as the primary mechanism for reporting to the Project Board lacked any financial information, with budgets being reported only in terms of days used. That being the case, where budgeted days were reported as overspent, there was no acknowledgement of the financial implications of this within the accompanying notes. By September 2004, the Highlight Reports had ceased to provide even the information on days spent. |
|
Para 39 |
The project has also suffered from a lack of profiling of costs, to enable the budget to be monitored against key deliverables and stages. There is no evidence of a coherent process for ‘sign off’ of budgets at pre-determined milestones. As a result, although actual expenditure could appear at times to have been in line with the current estimate, it was not sufficiently clear what had actually been delivered for the spend to date. |
|
Para 40 |
Highlight Reports now provide summary financial information clearly setting out the actual spend to date against the authorised budget, along with a forecast of the final position. Arrangements have been further strengthened by the inclusion of a representative from Corporate Finance on the Project Board. Had this been the case from the outset, the weaknesses in financial monitoring information in Highlight Reports may have been addressed at an early stage. |
|
Para 41 |
As noted above, the ACE’s May 2005 briefing for Members identified that ‘people costs’, largely funded from revenue budgets, were the primary area of cost overrun. The Council has well established procedures for monitoring performance on revenue budgets, involving the compilation of monthly reports by business unit managers, which are independently reviewed by Corporate Finance before the production of summary reports for discussion at chief officer level and the bi-monthly Finance and Performance (F&P) Reports to Members. |
|
Para 42 |
From these reports, it became apparent that the project was experiencing significant difficulties in containing costs within the original budget. However, as these costs were associated with a one-off, major capital project, the discussion of the issues arising appears to have occurred outside of the standard budgetary control procedures, at the level of the Chief Executive’s Management Board. |
|
Para 43 |
The existence of a substantial earmarked reserve, the IT Sinking Fund, provided a contingency which could be drawn upon. Also, at the same time as the extent of the overspend on the project was becoming clear, the Council was recording an underspend on its other revenue budgets against. The overspend of £2.9 million was offset against the IT sinking fund and expected revenue underspends. |
|
Para 44 |
In addition to the changes to Highlight Reports, greater clarity has now been introduced to budget monitoring at the corporate level. This is reflected in the current forecast of additional spending on revenue costs which, while of itself an indication of continuing issues with the realism of the budget, is also indicative of greater transparency in the financial management of the project. |
|
Para 45 |
It is essential that, for a project of this scale and strategic importance, financial reporting at the corporate level provides the Council’s leadership with clear and concise financial information. The primary sources through which Members could be updated on the financial position of the project were the F&P Reports and reports to the E-Government Advisory Committee (EAC). |
|
Para 46 |
Review of the financial content of a sample of EAC reports found that: · at the early stages, a brief comment that expenditure was being contained; and · at the later stages, when the difficulties were apparent to officers, no mention of the financial position of the project. |
|
Para 47 |
The reports prepared in 2005, such as F&P reports and the May ACE briefing, demonstrate confusion over the true picture of costs, with varying levels of over and underspends being reported. F&P reports also provided inadequate information about the Tech Refresh. As late as February 2005, the report stated that the Chief Executive’s department, which hosts the revenue element of the project budget, had a projected underspend of £0.4 million (as reported in April 2005). As noted above, the June 2005 outturn report identified a £2.6 million overspend for the department, including £2.9 million additional Tech Refresh costs. |
|
Para 48 |
As noted above, the Council’s overall underspend on the General Fund enabled the Tech Refresh overspend to be absorbed within the overall Consolidated Revenue Account for 2004/05. This was reported to Members via the 2004/05 annual accounts and the June 2005 outturn report. However, major increases appear to have occurred in the project estimates without the formal virements being made or reported, and the Council needs to review its procedures in this regard |
The criticisms set out above have been addressed in the Executive’s action plan of 21 February, in response to, in effect, all of the recommendations which, in different ways, are developments of our project and programme methodology. Members may wish to note that the project and programme methodology in place, even before the District Auditor’s recommendations, has been substantially improved over that in operation in 2003.
5. Who developed the budget: was it done in house, out of house or a combination.
This formed part of the District Auditor’s review and the conclusions are set out in paragraphs 21 – 23 of his report (see under question 2).
The production of the budget involved consultants and Council officers. Further information is set out under question 6.
6. Please indicate (if appropriate) the consultants used by Haringey to develop the project?
This formed part of the District Auditor’s review and the conclusions are set out in paragraphs 21 – 23 of his report (see under question 2).
The consultants involved in the preparation were Northgate and Deloittes. Independent review of the plans and proposals was carried out by Gartner.
7. Are their fees included in the overall cost of the project?
No. It is not normal practice in the Council to include project preparation costs in project budgets. As indicated at the 28 February meeting, the pre-project fees were approximately £150k.
8. How many meetings did the (then) Lead Member attend to discuss the progress of the commissioning phase?
The project was agreed by the Executive on 10 June 2003. The project was preluded in a report to the Executive on 18 June 2002 and was considered by the E-government Advisory Committee on 17 April 2003.
Appendix 2 shows the membership and frequency of the e-government advisory committee from 2002.
9. Who (in-house) comprised the project team?
The initial project structure is set out above paragraph 15 of the District Auditor’s report:
10. When was the project signed off and the
budget agreed?
At the Executive on 10 June 2003.
Project implementation
11. When did the Tech Refresh project start the implementation phase?
After the meeting of the Executive on 10 June 2003.
12. Outline the management controls and procedures that were set up to run the project? How well were they adhered to?
This formed part of the District Auditor’s review and the conclusions are set out in paragraphs 28-36 of his report. The report considers project assurance and change requests.
|
Para 28 |
Project assurance is the independent monitoring of the project progress and management on behalf of the Project Board to ensure the project is being well managed. The three main areas of project assurance are as: · business: monitoring the business case, business risks and expenditure; · technical: monitoring the use of standards and the quality of products; and · user: monitoring that the end product continues to meet the user’s specification throughout its development. |
|
Para 29 |
There has been little project assurance to date and it is not clearly defined within the project initiation document. As a consequence, it is unclear how the project board has ensured an ongoing robust independent overview of the project. |
|
Para 30 |
‘Scope creep’ is a change or growth to the original project and within large complex projects an element of this is reasonable. Should this occur, the project manager and board should work effectively to manage changes so as not to affect the project timelines and budget. From an early stage, there has been little challenge to scope creep within the Tech Refresh project. There is no clear audit trail of robust challenge through questioning of needs and wants, for example through the Project Board minutes, nor identification of the business benefit of change and the underlying issue making the change necessary. |
|
Para 31 |
The process for managing and authorising project change requests gives rise to a number of concerns. It is unclear what level of challenge was provided on behalf of the Council. Whilst the project board does not need to see all change requests, it needs to be aware of the overall quantum of changes and key individual items. It is clear that the Council’s Project Leader was able to authorise a significant amount of change requests before any form of scrutiny was applied. A number of change requests do not have a business sponsor. This suggests that the level of segregation between request and authorisation was not adequate. A significant weakness identified in this area is that a number of change requests have been submitted and approved retrospectively. |
|
Para 32 |
The lack of clarity around the status and control of change requests appears to have been a factor behind the cost overruns incurred by the project. The PID states that ‘any changes or deviation to the project that will impact on project timescales or budget will require a change request to be authorised before work will be scheduled or undertaken or curtailed.’ Change Request Forms are to be submitted to the Project Leader or Project Board ‘as appropriate’, without clear definition of what the ‘appropriate’ circumstances are. |
|
Para 33 |
To date, some 140 change requests have been raised on the project, with a cumulative value of some £7.1 million (excluding £113,000 of cancellations). Our review of a sample of the change requests provides evidence that the appropriate control was not exercised. Examples we identified included: · four requests account for £4.7 million of the changes, including £2.6 million for additional external support and £1.9 million for additional change management resources. It would be reasonable to expect changes of this magnitude to be considered at Project Board level, but the audit trail for any such discussions is lacking; and · retrospective requests, for example, £32,000 for the costs of running an information stall at the Council’s 2004 Summer Event. |
|
Para 34 |
It is essential to establish tolerance levels from the outset of the project – no project ever goes fully to plan and the project manager needs to have a clear understanding of when to escalate issues to the Project Board. Even with a good plan, elements will go astray. Tolerance is the permissible deviation from the plan without bringing the deviation to the attention of the next higher authority within the management structure. The two elements to tolerance are most commonly time and cost. |
|
Para 35 |
No clear predefined limits or tolerance levels have been laid down within the project. As a consequence, escalation of problems and issues appears to have been taken in an informal way or not at all. It is not clear whether a number of these issues were hidden, ignored or just not acted upon appropriately at an early stage or most probably a mixture of all three. |
|
Para 36 |
The status of change requests in terms of their impact on the project budget is also unclear. Finance officers have indicated that any additional costs arising from such changes need to be covered from existing allocated budgets, unless a virement is authorised by the Chief Accountant. However, the scale of additional costs arising from Change Requests, coupled with the absence of any reported virements to the project up to April 2005, would suggest that project staff were not sufficiently aware of this procedure. |
The criticisms set out above have been addressed in the Executive’s action plan of 21 February, in response to, in effect, all of the recommendations which, in different ways, are developments of our project and programme methodology. Members may wish to note that the project and programme methodology in place, even before the District Auditor’s recommendations, has been substantially improved over that in operation in 2003.
13. Please list the members of the Project Management Board and list their attendance at meetings.
This formed part of the District Auditor’s review and the conclusions are set out in paragraphs 15 of his report:
|
Para 15 |
An essential requirement of project board members is regular attendance at board meetings to ensure a robust decision making process is in place. Strong commitment from all members of the project board is essential to ensure that the appropriate lines of responsibility, accountability and reporting structures are in place and effective. This has not been the case, with poor attendance by some board members whose remit was to represent the Council’s interests. |
It is not normal practice to provide details relating to individual members of staff in open meetings.
The criticism set out above have been addressed in the Executive’s action plan of 21 February, in response to, recommendation 6 (corporate finance representation) and 8 (robustness of the project board).
14. Were outside consultants used to simply help run or did they fully run the project?
The project structure is set out above paragraph 15 of the District Auditor’s report (see question 9). This shows whether individuals were from the Council or external partners and clearly shows that the Council retained overall responsibility for the project.
15. Please tell this Committee how many reports to the lead member were received in 2003, 2004 and 2005.
It is not normal practice to comment on the activities of Executive Members in fulfilling their portfolio responsibilities other than where there are formal processes under the constitution. The formal governance of the project was charged in 2003 and 2004 to the E-government Advisory Committee which received reports on a regular basis.
Appendix 2 shows the membership and frequency of the e-government advisory committee from 2002.
16. It was due to finish in October 2004: please list all the factors that have prevented this from happening.
This formed part of the District Auditor’s review and his conclusions are set out through the report. The budget break down set out above (under question 3) provides an explanation of the cost overrun and the delay.
17. The Audit Commission refers to change management and variation orders as factors in the cost over runs. Please explain what these are and give the Committee some examples.
The position on change management is set out under note 2 of the budget analysis, namely: “Change was originally intended to be a Council function. The cost over run is because this had to be performed by Deloittes.”
The changes to the project were governed by change requests. The reasoning is set out above in the budget analysis, under question 3.
18. When did it become first apparent that the project was starting to overspend?
This formed part of the District Auditor’s review and the conclusions are set out in paragraphs 37 - 48 of his report (above under question 4). The reasoning and timing is set out above against the budget analysis (see question 3).
19. How was this information relayed (and when) to the Lead Member?
The formal reporting to members is set out in the answers above (question 15). The position on the reporting of the scale of the potential overspend is set out under question 24 and 25.
20. Did Haringey’s auditors pick up the overspend, if so when?
This question would need to be addressed to the District Auditor. To our knowledge, the District Auditor did not have concerns prior to our request to carry out a review.
The internal audit service, in its programme of work agreed by the Audit Committee, also did not identify any issues.
21. What actions were taken by the lead member and/or the Project Management Board to get the project back on course?
This formed part of the District Auditor’s review and the conclusions are set out in paragraph 10 of his report:
|
Para 10 |
The Council is now taking action to exercise greater control over this project. Actions include commissioning this review in order to learn lessons both for managing this project to its conclusion, as well as for other significant schemes, tightening project management and enhancing financial information. The Finance and Performance report to the November 2005 Executive suggests that there is further potential slippage and additional costs over budget to be incurred on the project in 2005/06. The Council needs to exercise tight financial control over the remaining life of the project, as well as applying the lessons learned to both this and other schemes. |
The response is further amplified in the answer to question 25.
22. Who was responsible for appointing a level 2 officer to take financial responsibility for this project, against accepted best practice?
The allocation of staff resources to deliver the Council’s objectives is a matter for the Head of Paid Service. The District Auditor’s views, set out at paragraph 16 of his report, are clear and were agreed by the Executive on 21 February 2006.
|
Para 16 |
The Tech refresh project was and remains a significant risk for the Council. The project sponsor is the ultimate Senior Responsible Officer for project approval and support and for ensuring that the overall strategic direction of the project is maintained. It would be expected that with a project of this size and risk the project sponsor would have been an executive board member of the Council. However, this was not the case, the project sponsor being the Head of ICT, a second tier officer. |
23. Have there been any staff disciplinary proceedings as a result of the project overspend and over run?
No.
24. Was
the chief executive made aware of the problems with the
project?
If so when was he made aware?
The Chief Executive was kept briefed through the life of the project through normal management processes, namely monthly budget management, 1:1s and programme management processes and the performance appraisal process. The scale of the potential overspend became clear in April 2005 and the Chief Executive was promptly informed.
25. Did David Warwick offer any advice, cautions or suggestions about how the Lead member should respond to the looming crisis? If given, what was the advice? When was this advice given? Was the advice acted on?
It is not normal practice to comment on advice given to Executive Members in fulfilling their portfolio responsibilities other than where there are formal processes under the constitution. In addition I was not the relevant Executive Member at the time. However, the advice and the response was to bring the project in-house and the fact that the project is now substantially complete demonstrates that this was the right thing to do.
26. Under exactly what circumstances did the previous project manager depart? Did he resign? If so, was there a financial pay-off? If so, what was the cost to the council?
It is not normal practice to provide details relating to individual members of staff in open meetings so further personal information is not being made available.
27. In view of the scale of the overspend, is the lead Member satisfied that it can be accounted for by management failures or did he ever consider the possibility of fraud? If so, what was done to look at this possibility?
As the Leader made clear in his answer to Council on 6 February 2006 there is no suggestion that this overspend is due to fraud. The Council’s normal processes in this regard has applied and, further to this, the project has been comprehensively reviewed by the District Auditor.
The Audit Commission report
28. When was the decision made to ask the Audit Commission to investigate this project?
July 2005.
29. How many other Haringey projects (IT and non-IT) been reviewed by the Commission?
The District Auditor determines his work programme on an annual basis. The programme and its product is regularly reported to the Council’s Audit Committee.
30. Who made that decision and on whose advice?
The Leader and Lead Member (ODPM), in discussion with the Interim Chief Executive.
31. Who (internal and external to Haringey) were interviewed by the Commission?
The District Auditor’s methodology is set out in paragraph 6 of his report.
|
Para 6 |
The review was carried out through: · A review of key documents; and · Interviews with key officers involved with the project. This did not include former employees or external partners or consultants. |
Post Commission report
32. What controls are now in place to ensure that best practice is now being followed and that these failures cannot happen again?
This is set out in the report to the Executive dated 21 February 2006, in response to the District Auditor’s report.
33. The Audit Commission says (Para 9) the “The Council cannot demonstrate that the full additional £10m costs represent value for money.” Does the Lead member believe that to be the case?
The views of the Executive have been comprehensively expressed by the Leader in his oral answer to Council on 6 February. Since this was an oral answer, I will quote:
“Let me take some time unpicking what the District Auditor has to say about value for money. The Auditor says, and I quote:
“the Council cannot demonstrate that the full additional [….] costs represent value for money”
Interesting words. Interesting because of some small words. Interesting that by using the word “full” the District Auditor is clearly accepting that at least some of the additional costs represent value for money. Interesting that, in my view, the District Auditor has missed out an important word. Of course we cannot yet demonstrate that the project has delivered value for money because when the District Auditor did his work the project wasn’t finished. Tonight, Mr Mayor, I will make a clear commitment. There will be a full post implementation review. I am charging my Executive Colleague, Councillor Sulaiman, to oversee that review. And the review will carefully consider whether the project has delivered value.”
34. What has been done to ensure clear audit trails?
The audit trails around, for example, finances, decisions and boards are clear and the Post Implementation Review will use this information. The information is stored within the Project Management Office and the Council’s financial systems.
35. How much has it cost the council to review its management procedures in the light of the Audit Commission report?
The cost of the review reported to the Executive on 21 February 2006 was, with the exception of the District Auditor’s review, primarily based on officer time.
The future
36. What is the current total cost of the IT Tech refresh project, from its inception to date, including costs absorbed by suppliers?
The relevant cost is the cost to the Council. This was re-budgeted in May 2005 (and agreed by the Executive on 10 June 2005) to £19.1m.
37. What is the likely /budgeted final cost likely to be?
This Committee is aware, from my written answer to a question (based on the Finance and Performance report to the 1 November Executive) asked at your meeting of 24 October 2005, that there was a risk of a £0.5m overspend on this year’s costs. This risk has largely crystallised so the projected spend this year is £5.5 million.
38. How will the Lead Member go about measuring whether the project has delivered what it set out to and will; he report this back to this Committee?
A full post implementation review will be carried out. This will be reported to the Executive. The agenda for this Committee in the next municipal year is clearly a matter for the Committee.
The purpose of the post implementation review will be to review the benefits realisation, assess value for money and to establish any specific or general learning points. I will be working on the terms of reference of this piece of work so that we are ready to commence the review early in the new administration.
Questions from Cllrs Hoban and Davies
39. Can he please confirm the chronology of events which led up to the council’s decision to ask the Audit Commission to undertake an investigation into the Tech Refresh project.
Please see Appendix C.
40. Who made the decision to commission the investigation and when?
See above (questions 28 and 29)
41. Could he confirm the exact role/s Deloitte has played in the Tech Refresh project, and does he consider that their role as the council’s contracted auditor could be seen to represent a conflict of interest?
The role of Deloittes is clearly set out in the report to the Executive on 10 June 2003. A different part of Deloittes is the Council’s internal auditor. The s151 (Director of Finance) officer satisfied himself at the time of contract award that the appointment did not represent a conflict of interest and it is my understanding that there is no reason to believe that it did or does represent a conflict.
Question from Cllr Dawson
42. It is my understanding that the IT budget does not exist as a service in its own right but that it relates to the operational performance of each and every Council directorate and business unit, therefore could the Executive Member for Organisational Development and Performance provide information on:
- IT provision (hardware and software) per Directorate
- Number of IT users per Directorate
- The assessments that have been carried out on the operational impact of IT provision and use within each Directorate.
There is a corporate IT budget which has, in the past, been thoroughly scrutinised by this Committee. This budget funds the majority of IT activity across the Council. The budget is recharged across the Council’s business units. The raison d’être of the budget is to provide support to the functions and activities of the Council. To do this, we support over 300 applications and nearly 5,000 assets, as set out below. The total number of users is around 5,700.
Applications (software excluding Access databases)
All Directorates (Core Applications): 36
More than 1 Directorate (Key Applications): 75
Used by 1 Directorate only (Non Core), being:
Environment 35
Finance 19
Chief Executive 78
Social Services 12
Children’s Service 37
Housing 15 196
Total 307
User log-ons and assets
|
|
Assets |
|
Chief Executive |
1462 |
|
Environmental Services |
497 |
|
Finance Services |
529 |
|
Housing Services |
710 |
|
The Children's Service |
504 |
|
Social Services |
1184 |
|
Total |
4886 |
IT is clearly pivotal in delivering the Council’s services and has been and will continue to be an underpinning factor in delivering improving and improved services. It is worth noting that during the period of the refresh project a wide range of service improvement projects have operated so that, for example,
The Council’s current IS/IT strategies were agreed in 2003 and it would not be untimely for these to be thoroughly reviewed by the next administration, following the election in May.
Questions from Cllr Brown
43. Could you please explain what systemic processes are in place to ensure that lead members are kept regularly informed of the state of the budgets within her/portfolio? Could you also explain how senior managers regularly check on budgets with their more junior budget holders and also how managers responsible for monitoring externally allocated contracts regularly check on the status of those budgets?
This formed part of the District Auditor’s review and the conclusions are set out in paragraphs 37 - 48 of his report (above question 4). The Executive’s response to the District auditor’s report was agreed on 21 February, the key responses to which I set out in my presentation.
Cllr Takki Sulaiman
Executive Member for Organisational Development and Performance
7 March 2006
|
|
Appendix A |
|
Action points from Overview and Scrutiny meeting – 28 February 2006 |
|
|
1.Cllr Winskill asked about officers being subject to disruption during Tech refresh but made a particular reference to: · Environmental Services being without systems for several days; and |
The plan for individual users was that very little productive time was lost as their desktops were swapped over. As you would expect, this plan was not always successfully delivered for a variety of reasons. It is difficult to be more specific without knowing the team to which the question refers. |
|
· Hornsey Library staff having just 5 work stations between 25 staff. Cllr Sulaiman, you offered to investigate this. |
The ratio of staff to workstations is a matter for individual business units. The number of workstations was a like for like replacement under Refresh. The Library Service is separately seeking additional workstations following Refresh. |
|
2.Cllr Winskill felt that the project dates provided on p2 of the answers to questions were inadequate and asked for a more detailed breakdown of dates; which should include details of all project meetings attended by the Lead Member, back to 2003. |
Now provided in Appendix B. |
|
3.Cllr Winskill asked to see the original detailed budget for the project as he felt that paragraph 24 of the Audit Commission Report was not detailed enough. Cllr Sulaiman, you suggested that Cllr Winskill would benefit from sight of the answer given to Cllr Williams on 19 July at Full Council last year and Cllr Winskill agreed to take this.Councillor Winskill also requested the projected overspend profile from 2005. |
Now provided. |
|
4. Cllr Winskill asked for the names of the smaller contractors involved in the project (as well as Gartner, Deloitte and Northgate). |
Now provided. |
|
5. Cllr Winskill asked for a copy of the original Gartner Report recommending the Tech Refresh project, back in 2002. |
Now provided. |
|
6. Cllr Winskill asked for the Director of Finance's and former CE's written responses to the overspend and any documents supplied to the Executive. Cllr Sulaiman, you agreed to this, provided the documents were not Exempt. |
Formal advice is set out in June 2005 Executive papers. |
|
7. Cllr Winskill asked about the Leaders investigation and report into Tech Refresh and asked if he could see the Terms of Reference for this. |
The terms of reference have not yet been finalised. |
|
Members then agreed to reconvene the meetinguntil the 9th March at 2:30 and discussed the format it should take as set out below:
|
Noted. |
|
The answers have been updated to integrate cross reference’s to the Executive’s response. |
|
Done. |
|
Noted. |
|
Noted, although ultimately the study will be sponsored by the Executive. |
|
|
Appendix B |
|
Membership and attendance at the e-government advisory committee 2003 - 2005 |
|
2002/03
Membership
Adje (Chair)
Basu
Bull
Meehan
Meetings
18 September 2002
17 October 2002
28 November 2002
17 April 2003 *
2003/04
Membership
Basu (Chair)
Adje
Makanji
Meehan
Meetings
13 October 2003 *
20 November 2003 *
5 February 2004 *
20 April 2004 *
2004/05
Membership
Basu (Chair)
Adje
Milner
Reith
Meetings
8 July 2004 *
12 October 2004 *
20 January 2005 *
* Indicates Tech Refresh on agenda.
|
|
Appendix C |
|
Refresh timelines
|
|
|
April 2003 |
Project planned and ready to go, on advice of Deloittes and Northgate. Independent review requested from Gartner Group and deliverability of solution and costings. Presentation to e-government advisory (17 April 2003). |
|
|
|
|
|
|
June 2003 |
Project agreed by Executive, following positive independent review. Haringey programme manager running project, Deloittes and Northgate mobilised. Project overseen by board with senior executive representation from three partners: the Council, Deloittes and Northgate. Project end date planned to be November 2004. |
|
|
|
|
|
|
July 2003 – May 2004 |
Project proceeding as planned. Issues being resolved and risks managed, with the exception from December 2003 of change management which was agreed as a Council responsibility and was not mobilising. Update reports to e-government advisory in July 2003 (flagging major dependency on accommodation strategy), October 2003 (flagging issues with the data centres location and slippage in change management activities), November 2003 (flagging issues with change management and emerging issue with the complexity of our application environment), February 2004 and April 2004 (providing updates on these areas). |
|
|
|
|
|
|
March 2004 |
Procurement approach agreed by Procurement Committee. Authority vested in ACE (Access). |
|
|
|
|
|
|
May 2004 |
Lack of change management activity identified as key barrier. Internal solution identified but not delivering. |
|
|
|
|
|
|
July 2004 |
Slippage of end date from December 2004 to March 2005 flagged to e-government advisory committee. Revised approach to change and deployment set out. |
|
|
|
|
|
|
July 2004 |
New data centres successfully built and operational. |
|
|
|
|
|
|
August 2004 |
Issues with procurement (planning ahead to hit time lines), management reporting to programme board, relationships between the three partners and Northgate input identified. Deloittes engagement extended to provide change management service. Project replanned and management reviewed. Revised project end date March 2005. Programme manager replaced and Northgate senior executive input changed, at our request. |
|
|
|
|
|
|
August 2004 – November 2004 |
Successful migration of exchange e-mail to archiving solution. |
|
|
|
|
|
|
September 2004 |
Active directory implemented. Active directory manages the user population. |
|
|
|
|
|
|
September 2004 |
First successful file structure migration. Other migrations have followed on as planned. |
|
|
|
|
|
|
October 2004 |
Refreshed environment deployed to IT department as a pilot. This demonstrated substantial problems with the stability and functionality of the build. Update to e-government advisory, flagging procurement of internet links as an issue. |
|
|
|
|
|
|
November 2004 |
Continuing problems with the build identified and concerns with the links with/transition to the live environment logged (both Northgate responsibilities). Considerable efforts required on relationship management.
|
|
|
December 2004 |
Review of programme by Council. Renewed commitment from partners to make project work. Approach adapted and end date shifted to May 2005. |
|
|
|
|
|
|
January 2005 |
Northgate input still causing concern. Escalated to Northgate Chief Executive. Replanning and further delays flagged to e-government advisory committee. |
|
|
|
|
|
|
February – March 2005 |
New Northgate team mobilised. Substantial concerns raised about quality of work to date and the volume of work required to hit plan. Amber status of project (with red on timescales) flagged to Member Working Group on Customer Services. |
|
|
|
|
|
|
April 2005 |
Risks which the Council would have to accept to hit plan articulated. Risks unacceptable. Delay in project required of further 12 weeks (end date December 2005). External partners disengaged. Council running programme direct. |
|
|
|
|
|
|
July – August 2005 |
Completed infrastructure successfully working in pilot area (IT Services). |
|
|
|
|
|
|
September 2005 |
First deployment to non-pilot area successfully completed. |
|
|
|
|
|
|
February 2006 |
Deployments substantially complete, and project close down with remaining activities, issues and risks passed to Business as usual operations.
|
|
Publication date: 02/03/2006
Date of decision: 28/02/2006
Decided at meeting: 28/02/2006 - Overview and Scrutiny Committee