Sites Financial Feasibility Appraisal: Request for contract award to GL Hearn.

Decision Maker: Assistant Director for Area Regeneration

Decision status: Recommendations Approved

Is Key decision?: No

Is subject to call in?: No

Decision:

For the Assistant Director for Area Regeneration to approve the contract award for a Wood Green Sites Financial Feasibility Appraisal commission to GL Hearn following a competitive tender process, for the sum of £44,050 + VAT.

Reasons for the decision:

The invitation to Tender attracted two high quality tenders from two consultants. GL Hearn scored the highest on quality and quantity.

Alternative options considered:

Procurement was carried out in line with procurement protocol. The alternative option was to appoint a consultant without following procurement protocol which may not have ensured best value.