Decision Maker: Assistant Director for Area Regeneration
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
Approval to
(i) allocate the HLF funding, as set out in Table 1 of the report
to the property owners and leaseholders in accordance with CSO
9.07.1c, and
(ii) approval to enter into Funding Agreements with the property
owners as set out at Table 1 in accordance with the Heritage
Lottery funding agreement.
Submission of the THI Bid to HLF was approved
by the Cabinet Member of Regeneration and Housing on 20 November
2014. The conditions of the council’s agreement with HLF
stipulate the need for a Works and Funding Agreement with owners
and tenants to secure 15% of the capital works budget.
The decision to award the works contract for Phase 1 of the North
Tottenham THI to Cuttle Construction Limited was approved by
Cabinet on 14 March 2017. The THI is a £2.3m project funded
by HLF £1.5m, Haringey Council £0.5m and property
owners £0.3m.
The Funding and Works Agreements with the owners, leaseholders and
business tenants of the properties will:
• secure the 15% contribution from owners towards the
conservation works
• commit owners to maintenance same for 10 years after
completion
To enable Heritage Lottery Fund (HLF) to release capital funds for
Phase 1 works, in accordance to our funding agreement with
HLF.
To not enter into contract would break the
conditions of council’s funding agreement with HLF to secure
15% of the capital works budget from owners and tenants. This would
risk a financial penalty.
Publication date: 04/04/2018
Date of decision: 03/04/2018