Decision Maker: Assistant Director for Corporate Property and Major Projects
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
Approve the implementation of Contract
Standing Order 10.02.1a and vary and increase the contract award to
deliver works at Riverside SEN School
To ensure Haringey Council can adhere to its
contractual obligations and make payment of contract
valuations
A do nothing option would mean that the
Council would be unable to make payment of the latest contract
valuation and would mean it would be in breach of its contractual
obligations
Publication date: 20/03/2017
Date of decision: 23/01/2017
Accompanying Documents: