Decision Maker: Director for Housing, Regeneration and Planning
Decision published: 15/09/2021
Effective from: 30/07/2021
Decision:
It is recommended that the Director of
Housing,
Regeneration and Planning, in consultation with the Cabinet Member
for House Building, Placemaking and Development:
i. Approve the final ballot programme
ii. Approve the Landlord Offer document, appended to this
report.
Lead officer: David Joyce
Decision Maker: Head of Programme Management
Decision published: 10/09/2021
Effective from: 02/08/2021
Decision:
Waiver of Contract Standing Order 10.01.1 and
contract award to Collage Arts to provide vocational training in
Creative and Design Industries and Digital Technology Industries at
Level 2 as part of delivery of Adult Education Budget (AEB)
contract with GLA for the amount of £15,901.61.
Lead officer: Liz Skelland
Decision Maker: Director for Housing, Regeneration and Planning
Decision published: 10/09/2021
Effective from: 02/08/2021
Decision:
That the Director of Housing, Regeneration and
Planning gives approval for the Council’s Legal Department to
enter into a Funding Agreement with L B Bexley – for the
funding of £800,000 to be released to undertake the above
high-speed broadband connectivity work.
Lead officer: David Joyce
Decision Maker: Director for Housing, Regeneration and Planning
Decision published: 20/08/2021
Effective from: 02/08/2021
Decision:
It is recommended that the Director of
Housing,
Regeneration and Planning:-
• Pursuant to CSO 9.07.1(c) approves the award of a contract
to Hughes & Salvidge Limited for demolition services (as
described in the report) for the sum of £119,500.00
• Approves the associated consultancy fees of up to
£38,022.50, payable to Ridge and Partners LLP.
Lead officer: David Joyce
Decision Maker: Assistant Director for Housing
Decision published: 18/08/2021
Effective from: 05/08/2021
Decision:
The Council’s current Housing Delivery
Programme Manager commences a secondment to the GLA from September
21 – May 22 leaving an urgent void to this key role to
support the delivery and manage the governance of the
Council’s number one priority programme. This report
therefore seeks approval to appoint Altair Advisory and Consultancy
Services Limited (‘Altair’) to provide Programme
Management services for the Housing Delivery Programme up to five
days a week for a duration of 9 months to aid delivery of the
Council’s ambition to build 1,000 council homes by
2022.
The total value of the contract will be up to £117,000. The
contract will start September 2021 and finish on May 2022.
Lead officer: Robbie Erbmann
Decision Maker: Head of Programme Management
Decision published: 16/08/2021
Effective from: 02/08/2021
Decision:
Direct award of contract for PPCR associates
to continue to deliver ITLA services on the Broadwater Farm estate;
waiver of Contract Standing Order (CSO) (requirement to tender)
under CSO 10.01.1
Contract to end 01.09.2022.
Lead officer: Liz Skelland
Decision Maker: Head of Programme Management
Decision published: 16/08/2021
Effective from: 02/08/2021
Decision:
That the Head of Programme Management for
Regeneration and Economic Development approve a contract award
under Contract Standing Order 8.02 to IKS Consulting Limited for
Quantity Surveyor services in relation to the enhancement of Page
Green Common (RIBA Stages 4-6) and of Page Green Terrace and
Rangemoor Open Space (RIBA Stages 1-2).
Lead officer: Liz Skelland
Decision Maker: Head of Programme Management
Decision published: 16/08/2021
Effective from: 26/07/2021
Decision:
To commission Haringey Basketball Association
under CSO 8.02 to manage the commission of an environmental health
and wellbeing programme for a 12-month period across Broadwater
Farm and Northumberland Park that will provide training
opportunities and peer to peer development. The commission is for
£4,000.
Lead officer: Liz Skelland
Decision Maker: Head of Programme Management
Decision published: 16/08/2021
Effective from: 26/07/2021
Decision:
Request for a waiver of Contract Standing
Order (CSO) (requirement to tender) under CSO 10.01.1 and award the
contract to The Lost Block Collective to provide a Youth Lead Media
Project as part of delivery programme for the Estate Regeneration
Fund Phase 3 (ERF) for the amount of £20,000
Lead officer: Liz Skelland
Decision Maker: Head of Highways and Parking
Decision published: 30/07/2021
Effective from: 29/07/2021
Decision:
To approve recommendations as set out in
Section 11 of this report.
Lead officer: Ann Cunningham
Decision Maker: Overview and Scrutiny Committee
Made at meeting: 06/07/2021 - Overview and Scrutiny Committee
Decision published: 26/07/2021
Effective from: 06/07/2021
Decision:
The Chair referred Members present to item one on the agenda in respect of filming at the meeting and Members noted the information contained therein.
Decision Maker: Head of Highways and Parking
Decision published: 23/07/2021
Effective from: 23/07/2021
Decision:
To approve recommendations as set out in
Section 10 of this report
Lead officer: Ann Cunningham
Decision Maker: Assistant Director for Housing
Decision published: 23/07/2021
Effective from: 22/07/2021
Decision:
It is recommended that the Assistant Director
of Housing, Regeneration and Planning approves the award of a
contract to New Ground Architects as allowed under CSO 9.07.1c (Bid
Acceptance and Contract Award) in the sum of £135,000
excluding VAT to provide Architect including Landscape Architect
services on the land in front of 2 – 240, Tiverton Road
housing delivery project.
Lead officer: Robbie Erbmann
Decision Maker: Assistant Director for Housing
Decision published: 23/07/2021
Effective from: 15/07/2021
Decision:
Pursuant to the Council’s Contract
Standing Order (CSO) 9.07.1(c), award a contract to Potter Raper
Partnership to create a BIM model for three high rise blocks. This
will be for the sum of £47,970.
Lead officer: Robbie Erbmann
Decision Maker: Assistant Director for Housing
Decision published: 23/07/2021
Effective from: 05/07/2021
Decision:
To approve the following decisions:
1. To implement Contract Standing Order 9.07.1 (c), which provides
that a Director may award, assign, or novate contracts valued at
less than £500,000 (five hundred thousand pounds) for the
purposes of appointing Calfordseaden to provide Mechanical and
Electricall Engineering services to the Sir Frederick Messer
Estate.
2. Award a contract to Calfordseaden for a total fee of
£128,581 (including specialist advice) + VAT.
Lead officer: Robbie Erbmann
Decision Maker: Assistant Director for Housing
Decision published: 23/07/2021
Effective from: 28/06/2021
Decision:
That the Assistant Director for Housing:
-
1) Approves the award of contract to Paragon Building Solutions
Ltd. for the quoted sum of £38,210 which includes a
contingency sum of 10% with a contract period of 8 weeks.
2) Approves the total project fees of £8,112.
3) Notes the total project cost of £46,322.
Lead officer: Robbie Erbmann
Decision Maker: Assistant Director for Housing
Decision published: 23/07/2021
Effective from: 21/06/2021
Decision:
That the Assistant Director for Housing:
-
1) Approves the award of contract to Paragon Building Solutions
Ltd. for the quoted sum of £69,098, which includes a 10%
contingency allowance within the tender sum with a contract period
of 12 weeks.
2) Approves the total project fees of £12,645.
3) Notes the total project cost of £81,743
Lead officer: Robbie Erbmann
Decision Maker: Head of Housing Development
Decision published: 23/07/2021
Effective from: 07/07/2021
Decision:
The Head of Housing Development approves the
award of a contract to Knight Frank as allowed under CSO 9.07.1c
(Bid Acceptance and Contract Award) in the sum of £36,000 +
VAT to provide Sales and Marketing Advise in regard to the Ashley
Rd Project, following a competitive procurement process.
Lead officer: Ana Blandford
Decision Maker: Head of Highways and Parking
Decision published: 23/07/2021
Effective from: 23/07/2021
Decision:
To approve recommendations as set out in
Section 11 of this report.
Lead officer: Ann Cunningham
Decision Maker: Assistant Director for Housing
Decision published: 23/07/2021
Effective from: 21/06/2021
Decision:
That the Assistant Director for Housing:
-
1) Approves the award of contract to Arlington Builders Ltd. for
the quoted sum of £14,149 which includes a contingency sum of
£1,415 and contract period of 6 weeks.
2) Approves the total project fees of £3,481.
3) Notes the total project cost of £17,630.
Lead officer: Robbie Erbmann