Decision Maker: Interim Assistant Director for Planning, Building Standards &Sustainability
Decision published: 15/10/2018
Effective from: 08/08/2018
Decision:
To authorise the Head of Legal Services to
prepare and seal a S.247 Agreement Under the Town and Country
Planning Act 1990 in relation to the Stopping Up of a section of
footway on Monument Way, which is within the demise of Transport
for London’s (TfL) Highway. The legal fees and costs
associated with the agreement is to be paid by the
applicant.
Lead officer: Emma Williamson
Decision Maker: Head of Operations
Decision published: 20/09/2018
Effective from: 10/08/2018
Decision:
To approve recommendations as set out in
Section 8 of the attached report.
Lead officer: Ann Cunningham
Decision Maker: Head of Operations
Decision published: 20/09/2018
Effective from: 15/08/2018
Decision:
To approve recommendations as set out in
Section 8 of this report
Lead officer: Ann Cunningham
Decision Maker: Director of Environment and Resident Experience
Decision published: 20/08/2018
Effective from: 02/08/2018
Decision:
For the Director Environment and
Neighbourhoods to approve the award of the contract for HFH 2018-19
Resurfacing Works to Kenson Contractors (Benington) Limited in the
sum of £111,759. 90 pursuant to Contract Standing Order (CSO)
9.07.1)(c), to approve a contingency of 10% of the contract value
(available in the borough maintenance budget) to cover unforeseen
works arising on site and the issuance of a letter of intent up to
a maximum value of £100,000 pursuant to CSO 9.07.3
Lead officer: Stephen McDonnell
Decision Maker: Director of Environment and Resident Experience
Decision published: 20/08/2018
Effective from: 02/08/2018
Decision:
For the Director Environment and
Neighbourhoods to approve the award of the contract for 2018/19
Borough Road Resurfacing Works to Kenson Contractors (Benington)
Limited in the sum of £425,174.40 pursuant to Contract
Standing Order (CSO) 9.07.1)(c), to approve a contingency of 10% of
the contract value (available in the borough maintenance budget) to
cover unforeseen works arising on site and the issuance of a letter
of intent up to a maximum value of £100,000 pursuant to CSO
9.07.3
Lead officer: Stephen McDonnell
Decision Maker: Head of Project Delivery
Decision published: 15/08/2018
Effective from: 24/07/2018
Decision:
This variation seeks approval to extend the
original award by £2,500, which is for the measured survey
work originally quoted at £4000. This equates to a 5% uplift
in the value of the contract.
The variation increases the total award value to £52,323.00
from £49,823.
Lead officer: David Moore
Decision Maker: Head of Project Delivery
Decision published: 15/08/2018
Effective from: 02/07/2018
Decision:
To approve the award of contract for
multi-disciplinary design services for the P1 Wave 1 Earlsmead
Primary School to Pellings LLP following direct call off from the
Fusion 21 Framework in accordance with CSO 7.01 for Framework
procurement arrangements.
The total value of the award is £49,408.00 which includes an
allowance of £4,000 for completion of a measured building
survey which was not included in the preceding feasibility stage
0-1 stage of the P1 Wave 1 urgent works commission.
Lead officer: David Moore
Decision Maker: Head of Project Delivery
Decision published: 15/08/2018
Effective from: 07/08/2018
Decision:
For the Head of Project Delivery to vary an
existing ward of contract to Frankham Consultancy Group (FCG) from
£42,468.71 to £44,678.71.
Lead officer: David Moore
Decision Maker: Head of Project Delivery
Decision published: 15/08/2018
Effective from: 07/08/2018
Decision:
Award of contract for undertaking remedial
works to the emergency lighting at Lordship Lane School to the
value of £2368.
Lead officer: David Moore
Decision Maker: Head of Operations
Decision published: 15/08/2018
Effective from: 14/08/2018
Decision:
To implement the proposed measures.
Lead officer: Ann Cunningham
Decision Maker: Head of Operations
Decision published: 14/08/2018
Effective from: 25/05/2018
Decision:
To approve recommendations as set out in
Section 9 of this report.
Lead officer: Ann Cunningham
Decision Maker: Head of Operations
Decision published: 14/08/2018
Effective from: 08/06/2018
Decision:
To approve recommendations as set out in
section 10 of this report
Lead officer: Ann Cunningham
Decision Maker: Head of Operations
Decision published: 14/08/2018
Effective from: 08/06/2018
Decision:
To approve recommendations as set out in
section 8 of this report.
Lead officer: Ann Cunningham
Decision Maker: Head of Operations
Decision published: 14/08/2018
Effective from: 25/05/2018
Decision:
Report of Statutory Consultation for the
relocation of an existing disabled bay in Kimberley Road N17 from
outside 32 to 34. Convert a shared Residents Permit Holders and pay
by phone parking space into shared permit holders and a pay by
phone operation in Glenwood Road N15.
Lead officer: Ann Cunningham
Decision Maker: Head of Operations
Decision published: 14/08/2018
Effective from: 08/06/2018
Decision:
To approve recommendations as set out in
section 8 of this report.
Lead officer: Ann Cunningham
Decision Maker: Head of Operations
Decision published: 14/08/2018
Effective from: 26/07/2018
Decision:
To implement the proposed measures.
Lead officer: Ann Cunningham
Decision Maker: Director of Environment and Resident Experience
Decision published: 10/08/2018
Effective from: 02/08/2018
Decision:
For the Director Environment and
Neighbourhoods to approve the award of contract for 2018/19
Principal and Classified Road Resurfacing Works to Kenson
Contractors (Benington) Limited in the sum of £445,960.85
pursuant to Contract Standing Order (CSO) 9.07.1)(c), to approve a
contingency of 10% of the contract value (available in LIP
Principal Road and Haringey Borough Road maintenance budgets) to
cover unforeseen works arising on site and the issuance of a letter
of intent up to a maximum value of £100,000 pursuant to CSO
9.07.3.
Lead officer: Stephen McDonnell
Decision Maker: Director for Housing and Growth
Decision published: 06/08/2018
Effective from: 05/07/2018
Decision:
For the Director of Housing & Growth to
waive CSO 8.02 and award the contract for the Provision of Electric
vehicles trials for Neighbourhood of the Future project Wood Green
to DriveElectric, Fleetdrive Management Ltd.
Lead officer: Dan Hawthorn
Decision Maker: Assistant Director for Area Regeneration
Decision published: 06/08/2018
Effective from: 25/07/2018
Decision:
Approval to enter into contract with ASB-MCM
UK Construction Ltd (“ASB”) for up to £20,000 to
undertake structural works at 1 and 5 White Hart Lane
N17.
Lead officer: Jordanne Robinson
Decision Maker: Head of Operations
Decision published: 03/08/2018
Effective from: 03/08/2018
Decision:
To implement the proposed measures.
Lead officer: Ann Cunningham
Decision Maker: Head of Project Delivery
Decision published: 03/08/2018
Effective from: 02/07/2018
Decision:
To approve the award of contract for
multi-disciplinary design services for the P1 Wave 1 Seven Sisters
Primary School to Pellings LLP following direct call off from the
Fusion 21 Framework in accordance with CSO 7.01 for Framework
procurement arrangements.
The total value of the award is £36,276.00 which includes an
allowance of £4,000 for completion of a measured building
survey which was not included in the preceding feasibility stage
0-1 stage of the P1 Wave 1 urgent works commission.
Lead officer: David Moore
Decision Maker: Interim Assistant Director for Planning, Building Standards &Sustainability
Decision published: 03/08/2018
Effective from: 20/06/2018
Decision:
Member’s agreement to pay Beveridge
Associates their fees for the services of their
mechanical/electrical engineer’s in checking the work at the
new THFC stadium.
Lead officer: Emma Williamson
Decision Maker: Head of Project Delivery
Decision published: 03/08/2018
Effective from: 02/07/2018
Decision:
To approve the award of contract for
multi-disciplinary design services for the P1 Wave 1 Bruce Grove
Primary School to Pellings LLP following direct call off from the
Fusion 21 Framework in accordance with CSO 7.01 for Framework
procurement arrangements.
The total value of the award is £49823.20 which includes an
allowance of £4,000 for completion of a measured building
survey which was not included in the preceding feasibility stage
0-1 stage of the P1 Wave 1 urgent works commission.
Lead officer: David Moore
Decision Maker: Head of Project Delivery
Decision published: 03/08/2018
Effective from: 26/07/2018
Decision:
For Head of Project Delivery to vary an
existing award of contract to Pellings LLP for the commissioning
and delivery of surveys to support feasibility studies across four
school sites
Lead officer: David Moore
Decision Maker: Pensions Committee and Board
Made at meeting: 23/07/2018 - Pensions Committee and Board
Decision published: 02/08/2018
Effective from: 23/07/2018
Decision:
The Committee considered the report, introduced by Thomas Skeen, which provided an update on voting activities on behalf of the Fund. The Committee noted that the Fund was a member of the LAPFF and the Committee and Board has previously agreed that the Fund should cast its votes at investor meetings in line with LAPFF voting recommendations.
It was noted that the voting shareholders are encouraged to act ethically and responsibly and to vote accordingly. Whilst it is not possible to force fund managers to vote a particular way, the Fund was able to strongly advise them of the position it feels they should take. It was acknowledged that this advice is generally adhered to and voting is, more often than not, done in line with the Fund’s position.
In discussion, the question was raised about what happened when a fund manager did not vote in line with the Fund’s preferred position. In response, it was noted that, whilst the Fund is unable to force fund managers to vote a particular way, it is mandatory for fund managers to provide detailed reasoning when their vote is that against the preferred choice of the Fund. It was suggested that it might be helpful if future Pensions Committee and Board meetings were provided with an update on the rationale behind why some companies vote in a different way to how the Fund would like them to vote.
The Committee and Board questioned how effective it was to ask companies to vote a certain way, with particular reference drawn to Anadarko, which votes in compliance with the Fund’s position only 52% of the time. The Committee was assured that engagement with companies is helpful and can have a positive investment impact. It was also highlighted to the Committee that engagement with companies is important in getting them to change their behaviour.
Resolved
The Committee note this report.
Decision Maker: Pensions Committee and Board
Made at meeting: 23/07/2018 - Pensions Committee and Board
Decision published: 02/08/2018
Effective from: 23/07/2018
Decision:
The Committee and Board considered a report, introduced by Thomas Skeen, on the governance update on the London Collective Investment Vehicle (CIV) governance structure and on the terms of appointments to the Pensions Committee and Board.
The Committee noted the changes in the governance structure of CIV, notably:
· General meetings, which all of the boroughs attend, will be held twice annually. These meetings will be in July (to approve the accounts), and in January (to approve the Medium Term Financial Strategy). These meetings will continue to be attended by either the Chair or Vice Chair of Haringey Pensions Committee and Board.
· Shareholder Committees will meet on a quarterly basis on a consultative capacity only, with 12 Shareholders represented: four S151 Officers, and eight Pension Chairs. The Pension Chairs would be selected via the collective political processes of the London Councils, providing political, geographical and gender diversity.
It was noted that, under the old system of governance, problems arose due to the sheer number of shareholders (32) trying to make decisions. The new structure of four S151 Officers and eight Pension Chairs was expected to create more effective dialogue by streamlining the number of participants in the decision making. Haringey Council did initially challenge the selection process of the eight Pension Chairs and questioned whether this would secure the best individuals for the committee.
In discussing the selection of the eight Pensions Chairs to attend the quarterly meetings of the shareholder committees, it was noted that, contrary to the objective of selecting chairs that reflect the political balance of London, the proposed chairs do not in fact do this. It was further noted that it was important for the Chair of the Pensions Committee and Board to build effective working relationships with the other Pension Committee Chairs.
Terms of appointment for the Pension Committee and Board
The Chair gave an update on the terms of appointment to the Pensions Committee and Board. Regarding his discussion with both Chief Whips, it was acknowledged of the need for continuity to ensure that members have the necessary knowledge and training to sit on the committee. Both Chief Whips have stated that they are committed to appointing the same members onto the Pensions Committee and Board each year within the election cycle, while recognising that Groups may wish to hold elections for their nominees for the Chair and Vice Chair positions. It was suggested that this would be a better alternative to the cumbersome approach of changing the Constitution of the Council to mandate 4 year terms for members of the Pensions Committee and Board. The Chair stated that this would be reviewed in 2 years’ time to ensure that this approach is still a workable and effective one. However, it was noted in discussion that this approach only works for members of the Pensions Committee and Board who wish to remain on the committee.
Resolved
That the Committee and board:
Decision Maker: Pensions Committee and Board
Made at meeting: 23/07/2018 - Pensions Committee and Board
Decision published: 02/08/2018
Effective from: 23/07/2018
Decision:
The Committee considered this report, presented by Janet Richards, which detailed potential new admissions to the pension fund. The Committee noted in the report:
· the steady increase of users visiting Haringey Website.
· the most recent internal audit of the pensions administration service, which showed a substantial assurance rating of the service, this is for members to note.
· the update to the Pensions Administration Discretionary statement to make it clear that Haringey Council will exercise the discretion to abate the pensions of former employees who are retired early, if they are re-employed by any of the scheme employers in the Haringey LGPS Pension fund.
The Committee was informed that this was a regular item on the agenda and that there were certain areas that needed improving, such as employer’s provision of information to the fund.
It was drawn to the Committee’s attention that, since the publication of the report, there was a new school in Haringey that had started to make some contribution to the Fund.
It was queried why, on page 235 of the Report Pack, Standing data was ‘Amber’ and not ‘Green’ (signalling weaker effectiveness of controls). It was noted that attaining information from outside providers can be challenging, and there are various factors that impact the delay or lack of information, such as turnover of staff.
In response to a question regarding the potential admissibility of new employees of ISS Mediclean Ltd as fund members, it was noted that this admission to the fund would be on a closed basis, meaning that new members of staff not employed on the date of the admission would not be eligible to join the fund.
Resolved
That the Committee:
Reason for decision
New Admission Body to the Fund
ISS Mediclean Ltd
West Green School has tendered its cleaning service and the successful bidder was ISS Mediclean Limited. It is proposed that ISS Mediclean be admitted to the Haringey Pension Scheme as an Admission Body in relation to the provision of the cleaning Service for West Green School, subject to ISS Mediclean Ltd entering into an admission agreement with the Council so that those eligible employees can remain within the Haringey Pension Fund.
That an admission agreement satisfactory to the Council be entered into – in respect of the service contract and that the agreement is a closed agreement, as such that new members cannot be admitted.
The Employer contribution rate is 29% and the bond is £50,000. The staff are required to work no less than 50% of the time on their contract.
Haringey Education Partnership
Haringey Council has made a decision to commission statutory and strategic school improvement functions, and has entered into a contract with Haringey Education Partnership (HEP), under which HEP will carry out those functions for the Council.
It is proposed that HEP be admitted to the Haringey Pension Scheme as an Admission Body from 1 September 2018, subject to HEP entering into an admission agreement with the Council that is satisfactory to the Council, so that those employees designated by HEP as eligible will be entitled to be members of the Haringey Pension Fund.
Under Regulation 3(1)(iii) of the LGPS Regulation 2013, HEP has designated a class of employee eligible to join the pension scheme.
The designated eligible employees that the admission agreement will be open to are the Governor Support Officers and the Senior Governor Support Officers. The admission agreement will be closed to all other employees of HEP.
HEP will be included within the Haringey Council pool of employers, and they will pay the same employer contribution rate as Haringey Council, which is currently 24.9%.