Cabinet considered a report that presented a
proposed budget package for 2012/13 and later years. The report
also included an overview of the Medium Term Financial Plan (MTFP),
which covered the three years to March 2015, including a revised
assessment of the General Fund, Dedicated Schools Grant (DSG),
Housing Revenue Account (HRA) and the Capital Programme.
It was noted that the proposals included
funding from the Capital Programme to enable Alexandra Palace to
develop of long term strategy and regeneration and development
programme. This was considered essential in order to form a long
term approach that would help reduce the financial support that the
Council had a statutory obligation to provide.
RESOLVED:
- That the recommendations of the
Overview and Scrutiny Committee on the chosen three themes of the
draft revenue proposals agreed at the Cabinet meeting held on 4
October 2011 (set out in paragraphs 7.9 and 7.12 and Appendix 7 of
the report) be noted.
- That the consultation responses
received to date on the draft revenue proposals agreed at Cabinet
on 4 October 2011 (set out in paragraphs 7.1 to 7.8 and Appendix 8
of the report) be noted.
- That the implications for the
Council of the Provisional Local Government Finance Settlement
2012/13 (set out in paragraphs 8.4 to 8.31 and Appendix 4 of the
report) be noted.
-
- That the indicative
level of the Dedicated Schools Grant (DSG) for 2012/13 (set out in
paragraph 12.3 of the report) be agreed.
- That the expected
Pupil Premium allocation of £10.1m (set out in paragraph 12.4
of the report) be noted.
- That the approach to
universal grants and targeted grants (set out in paragraph 12.5 of
the report) be agreed.
- That the treatment of
the one off allocations of £522k in 2012/13 (as set out in
paragraph 12.7 of the report) be endorsed.
- That the intention of
the Schools Forum to consult and to propose changes to the Formula
following consultation (as set out in paragraph 12.8 of the report)
be noted.
- That the funding of
the items (as set out in paragraph 12.10 of the report) from the
available headroom be agreed.
- That the approach to
the use of headroom (as set out in paragraph 12.12 of the report)
be agreed.
- That the changes in the financial
management of the HRA from 1 April 2012 (as set out in paragraphs
2.1 to 2.5 of the report) be noted.
- That the background to the Stock
Options Appraisal (as set out in paragraphs 3.1 to 3.7 of the
report) be noted.
- That the proposed housing rent
increases (as set out in paragraphs 4.1 to 4.10 of Appendix 5 of
the report), which were subject to consultation, be noted.
- That the proposed tenants’
service charges (as set out in paragraphs 5.1 to 5.3 of Appendix
5), which were subject o consultation, be noted.
- That the methodology to be used to
separate the outstanding debt on 1 April 2012 between the HRA and
the General Fund (as set out in paragraphs 6.1 to 6.8 of Appendix
5) be agreed.
- That the draft HRA Budget 2012/13
and MTFP 2012-15 for recommendation to the Council at its meeting
in February 2012 (as set out in paragraphs 7.1 to 7.7 of Appendix 5
of the report) be approved.
- That draft proposals to be
recommended to the Council at its meeting in February 2012 for the
Council’s Capital Programme for the period 2012-15 (as set
out in paragraph 14 and Appendix 6 of the report) be approved.
- That it be noted that the Cabinet
would, at its meeting in February, assess the need to make
additional proposals for the MTFP 2012-15, to be recommended to the
Council for approval, in the light of circumstances at that
time.
- That draft proposals, to be
recommended to the Council at its meeting in February 2012 for the
Council’s MTFP 2012-15 (as set out in Appendices 1, 2 and 3
of the report) be approved.
- That it be noted that savings still
had to be identified to deliver a balanced budget for
2013/14.